Garfield-Harrison Project
The Garfield-Harrison Project is a large-scale master planned Stormwater project that began in January 2022. The City of Loveland has contracted with Connell Resources to build the Garfield Harrison Storm Drainage Improvements Project. The four separate phases are expected to occur over the next four years (approximately one phase per year.) The project addresses the multiple drainage problems caused by aging infrastructure in the west part of downtown Loveland. Partnering with the City’s Water and Wastewater divisions, Street Maintenance and Rehabilitation Program, and Stormwater Engineering, the project will include new waterlines, sanitary sewers, street resurfacing, and various concrete repairs that will improve ADA accessibility.
The four-year project is designed to improve the following:
- Implementation of the City of Loveland Master Drainage Plan
- Replacing and upgrading existing stormwater infrastructure to address existing drainage issues and meet current stormwater standards
- Installing 18- to 60-inch diameter storm sewer pipes
- Replacing existing waterlines and valves to address aging infrastructure
- Replacing pavement including asphalt patching, milling, overlays, or full street reconstruction where project components are installed
- Rehabilitating and replacing concrete, as well as adding necessary ADA improvements
- Disconnecting stormwater from the Little Barnes Ditch during Phase 4
- Providing stormwater quality treatment measures within the stormwater system
The four-phase project is expected to be completed in fall 2027.
Phase 3
Work on Phase 3 is well underway with construction. The project includes five work zones for Phase 3 and will finish in early August 2025.
- Zone 1 - Roosevelt Avenue between 5th and 8th Street: Roadway will be closed to install new stormwater and waterlines. Zone 1 is estimated to be completed by spring 2025.
- Zone 2 - 8th Street between Sheridan Avenue and Harrison Avenue: The roadway will be closed to install new stormwater. Zone 2 is estimated to be completed spring 2025.
- Zone 3 - 7th Street between Franklin Avenue and Roosevelt Avenue: The roadway will be closed to install new stormwater. Zone 1 is estimated to be completed spring 2025.
- Zone 4 - Colorado Avenue between 7th Street and 8th Street and Franklin Avenue between 7th Street and 8th Street, 7th Street between Franklin and Colorado will undergo a full road closure to add to the continuation of installing the new stormwater. Zone 4 is estimated to be completed by late summer 2025.
- Zone 5 - 8th Street between Duffield Avenue and Colorado Avenue: The roadway will be closed to install new stormwater. Zone 5 is estimated to be completed by spring 2026.
A large-diameter storm sewer pipe will be installed on North Roosevelt Avenue to West 9th Street and then a smaller-diameter lateral west on West 7th Street to Colorado Avenue. Additionally, the project will include adding a new waterline on North Roosevelt Avenue between West 5th Street and West 8th Street. Under the five work zones, road closures in blocked segments will be required to install the new water and stormwater pipelines. The road closures will follow the timeline of the work zones.
During construction, local access, deliveries, and services will always be maintained. Residents will experience construction noise and disruptions near their homes. Traffic control personnel will be onsite to direct residents during this work. Typical working hours will be Monday through Friday from approximately 7 a.m. to 5 p.m. Night and weekend work will be occasional and announced in advance.
Learn about the phasing of this project
How is this project funded?
- Estimated total project cost: $18 million
- The project is funded through the Stormwater and Water Enterprise Fund. Enterprise funds are dedicated funds supported by user fees in the monthly utility bill. Similar to a business, user fees fund the operation, maintenance, administration, and capital improvement projects required to provide the service.
Stay Informed
To stay informed about this project, subscribe to our email list in the "Stay Informed" section. For immediate questions or concerns, contact us at: garfieldharrisonstormdrain@gmail.com or 970-716-5155. Please allow us at least 24-48 hours to respond to you. Thank you!
The Garfield-Harrison Project is a large-scale master planned Stormwater project that began in January 2022. The City of Loveland has contracted with Connell Resources to build the Garfield Harrison Storm Drainage Improvements Project. The four separate phases are expected to occur over the next four years (approximately one phase per year.) The project addresses the multiple drainage problems caused by aging infrastructure in the west part of downtown Loveland. Partnering with the City’s Water and Wastewater divisions, Street Maintenance and Rehabilitation Program, and Stormwater Engineering, the project will include new waterlines, sanitary sewers, street resurfacing, and various concrete repairs that will improve ADA accessibility.
The four-year project is designed to improve the following:
- Implementation of the City of Loveland Master Drainage Plan
- Replacing and upgrading existing stormwater infrastructure to address existing drainage issues and meet current stormwater standards
- Installing 18- to 60-inch diameter storm sewer pipes
- Replacing existing waterlines and valves to address aging infrastructure
- Replacing pavement including asphalt patching, milling, overlays, or full street reconstruction where project components are installed
- Rehabilitating and replacing concrete, as well as adding necessary ADA improvements
- Disconnecting stormwater from the Little Barnes Ditch during Phase 4
- Providing stormwater quality treatment measures within the stormwater system
The four-phase project is expected to be completed in fall 2027.
Phase 3
Work on Phase 3 is well underway with construction. The project includes five work zones for Phase 3 and will finish in early August 2025.
- Zone 1 - Roosevelt Avenue between 5th and 8th Street: Roadway will be closed to install new stormwater and waterlines. Zone 1 is estimated to be completed by spring 2025.
- Zone 2 - 8th Street between Sheridan Avenue and Harrison Avenue: The roadway will be closed to install new stormwater. Zone 2 is estimated to be completed spring 2025.
- Zone 3 - 7th Street between Franklin Avenue and Roosevelt Avenue: The roadway will be closed to install new stormwater. Zone 1 is estimated to be completed spring 2025.
- Zone 4 - Colorado Avenue between 7th Street and 8th Street and Franklin Avenue between 7th Street and 8th Street, 7th Street between Franklin and Colorado will undergo a full road closure to add to the continuation of installing the new stormwater. Zone 4 is estimated to be completed by late summer 2025.
- Zone 5 - 8th Street between Duffield Avenue and Colorado Avenue: The roadway will be closed to install new stormwater. Zone 5 is estimated to be completed by spring 2026.
A large-diameter storm sewer pipe will be installed on North Roosevelt Avenue to West 9th Street and then a smaller-diameter lateral west on West 7th Street to Colorado Avenue. Additionally, the project will include adding a new waterline on North Roosevelt Avenue between West 5th Street and West 8th Street. Under the five work zones, road closures in blocked segments will be required to install the new water and stormwater pipelines. The road closures will follow the timeline of the work zones.
During construction, local access, deliveries, and services will always be maintained. Residents will experience construction noise and disruptions near their homes. Traffic control personnel will be onsite to direct residents during this work. Typical working hours will be Monday through Friday from approximately 7 a.m. to 5 p.m. Night and weekend work will be occasional and announced in advance.
Learn about the phasing of this project
How is this project funded?
- Estimated total project cost: $18 million
- The project is funded through the Stormwater and Water Enterprise Fund. Enterprise funds are dedicated funds supported by user fees in the monthly utility bill. Similar to a business, user fees fund the operation, maintenance, administration, and capital improvement projects required to provide the service.
Stay Informed
To stay informed about this project, subscribe to our email list in the "Stay Informed" section. For immediate questions or concerns, contact us at: garfieldharrisonstormdrain@gmail.com or 970-716-5155. Please allow us at least 24-48 hours to respond to you. Thank you!
-
Project updates 6/8/26 - 6/12/26
Share Project updates 6/8/26 - 6/12/26 on Facebook Share Project updates 6/8/26 - 6/12/26 on Twitter Share Project updates 6/8/26 - 6/12/26 on Linkedin Email Project updates 6/8/26 - 6/12/26 linkHello Stakeholders,
Below are project updates from this week, as well as for the upcoming week (June 8th - 12th):- A walkthrough was conducted with the landscaping contractor to review remaining restoration work along 10th and 11th Streets, and Franklin, Roosevelt, Harrison and Colorado Avenues. The team also reviewed the West 10th Street segment between Colorado and Douglas Avenues to prepare for landscaping work that will be needed in the coming weeks.
- The concrete crew completed repairs to several inlets and applied grout around pipe connections within the inlet structures.
- We are awaiting the completion of construction surveying to determine what improvements will be needed along the north side of West 10th Street between Douglas Avenue and Lynx Drive. Design modifications were made to ensure proper roadway drainage, and the survey results will help guide the next phase of work.
- Paving is now complete on 10th Street east of Colorado Avenue, including the intersection of Colorado Avenue and 10th Street.
- The project team will review the revised plans for West 10th Street and then begin removing sidewalk sections and preparing the roadway for new curb, gutter and sidewalk improvements along the north side of the street.
- Project staff continue to communicate with property owners along the Little Barnes Ditch, providing updates on current work activities and available project information. This outreach is intended to keep residents informed and address concerns that have been raised to City Council members.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.
Hello Stakeholders,
Below are project updates from this week, as well as for the upcoming week (June 8th - 12th):- A walkthrough was conducted with the landscaping contractor to review remaining restoration work along 10th and 11th Streets, and Franklin, Roosevelt, Harrison and Colorado Avenues. The team also reviewed the West 10th Street segment between Colorado and Douglas Avenues to prepare for landscaping work that will be needed in the coming weeks.
- The concrete crew completed repairs to several inlets and applied grout around pipe connections within the inlet structures.
- We are awaiting the completion of construction surveying to determine what improvements will be needed along the north side of West 10th Street between Douglas Avenue and Lynx Drive. Design modifications were made to ensure proper roadway drainage, and the survey results will help guide the next phase of work.
- Paving is now complete on 10th Street east of Colorado Avenue, including the intersection of Colorado Avenue and 10th Street.
- The project team will review the revised plans for West 10th Street and then begin removing sidewalk sections and preparing the roadway for new curb, gutter and sidewalk improvements along the north side of the street.
- Project staff continue to communicate with property owners along the Little Barnes Ditch, providing updates on current work activities and available project information. This outreach is intended to keep residents informed and address concerns that have been raised to City Council members.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.
-
Project updates 6/1/26 - 6/5/26
Share Project updates 6/1/26 - 6/5/26 on Facebook Share Project updates 6/1/26 - 6/5/26 on Twitter Share Project updates 6/1/26 - 6/5/26 on Linkedin Email Project updates 6/1/26 - 6/5/26 link
Hello Stakeholders,
Below are project updates from this week and the upcoming week (6/1/26 - 6/5/26):
- Concrete repairs were completed on Roosevelt and 11th Street and on the south side of West 10th Street from Colorado to Douglas.
- Subgrade prep work is underway at the Colorado and 10th Street intersection prior to paving, along with prepping 10th Street east of Colorado.
- Paving crew raised two manholes that were buried (one on 8th Street and the other on Colorado and 4th Street).
- Paving crew paved Colorado and 10th Street intersection and put a bottom lift and leveling coarse on the 10th Street section east of Colorado. They will also pour concrete on mailbox pads on the west section of 10th Street.
- Survey was completed on both sides of west 10th Street to help finalize work needed along the west 10th Street section.
- Landscaping crew will return to complete work on 11th Street and also prep for west 10th Street.
Image Caption
Important Notice:
Upcoming Temporary Closure at 8th Street and Colorado Avenue IntersectionCity crews will repair a leaking water valve at the intersection of west 8th Street and Colorado Avenue starting next week. Because the damaged valve is in the middle of the intersection, the intersection will be closed during repairs from Tuesday through Thursday, weather permitting. Residents should expect delays and should detour to Taft or Garfield Avenues.
Starting Tuesday, crews will dig around the 12-inch water main to prepare for a new valve installation. On Wednesday, the Utilities contractor will install a temporary valve to help keep water service running for nearby customers during the repair work. For questions about the repair or water services, contact the Utilities Department at 970-962-3000.
Hello Stakeholders,
Below are project updates from this week and the upcoming week (6/1/26 - 6/5/26):
- Concrete repairs were completed on Roosevelt and 11th Street and on the south side of West 10th Street from Colorado to Douglas.
- Subgrade prep work is underway at the Colorado and 10th Street intersection prior to paving, along with prepping 10th Street east of Colorado.
- Paving crew raised two manholes that were buried (one on 8th Street and the other on Colorado and 4th Street).
- Paving crew paved Colorado and 10th Street intersection and put a bottom lift and leveling coarse on the 10th Street section east of Colorado. They will also pour concrete on mailbox pads on the west section of 10th Street.
- Survey was completed on both sides of west 10th Street to help finalize work needed along the west 10th Street section.
- Landscaping crew will return to complete work on 11th Street and also prep for west 10th Street.
Image Caption
Important Notice:
Upcoming Temporary Closure at 8th Street and Colorado Avenue IntersectionCity crews will repair a leaking water valve at the intersection of west 8th Street and Colorado Avenue starting next week. Because the damaged valve is in the middle of the intersection, the intersection will be closed during repairs from Tuesday through Thursday, weather permitting. Residents should expect delays and should detour to Taft or Garfield Avenues.
Starting Tuesday, crews will dig around the 12-inch water main to prepare for a new valve installation. On Wednesday, the Utilities contractor will install a temporary valve to help keep water service running for nearby customers during the repair work. For questions about the repair or water services, contact the Utilities Department at 970-962-3000.
-
Project updates 5/18/26 - 5/22/26
Share Project updates 5/18/26 - 5/22/26 on Facebook Share Project updates 5/18/26 - 5/22/26 on Twitter Share Project updates 5/18/26 - 5/22/26 on Linkedin Email Project updates 5/18/26 - 5/22/26 link
Hello Stakeholders,
Below are project updates from this week, as well as for the upcoming week (May 18th-22nd):
- The concrete crew continued working in sections along the south curb and gutter on 10th Street between Colorado Avenue and Douglas Avenue and also completed the sidewalk sections started last week.
- No storm pipe was installed this week, as pipe installation was completed two weeks ago. However, crews did place riprap at the outlet structure along the channel near 1st Street.
- The concrete crew has also been busy removing and replacing residential and apartment complex entrances while coordinating access with residents throughout construction.
- Concrete work has begun at the intersection of Colorado Avenue and 10th Street and will continue next week, including installation of ADA ramps, sidewalk, curb, gutter and cross pans.
- The base crew is expected to return late next week to begin removing asphalt along 10th Street, as well as the north-side sidewalk and entrances, in preparation for new sidewalk, curb, gutter and roadway paving.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.


Hello Stakeholders,
Below are project updates from this week, as well as for the upcoming week (May 18th-22nd):
- The concrete crew continued working in sections along the south curb and gutter on 10th Street between Colorado Avenue and Douglas Avenue and also completed the sidewalk sections started last week.
- No storm pipe was installed this week, as pipe installation was completed two weeks ago. However, crews did place riprap at the outlet structure along the channel near 1st Street.
- The concrete crew has also been busy removing and replacing residential and apartment complex entrances while coordinating access with residents throughout construction.
- Concrete work has begun at the intersection of Colorado Avenue and 10th Street and will continue next week, including installation of ADA ramps, sidewalk, curb, gutter and cross pans.
- The base crew is expected to return late next week to begin removing asphalt along 10th Street, as well as the north-side sidewalk and entrances, in preparation for new sidewalk, curb, gutter and roadway paving.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.


-
Project Updates 5/11/26 - 5/15/26
Share Project Updates 5/11/26 - 5/15/26 on Facebook Share Project Updates 5/11/26 - 5/15/26 on Twitter Share Project Updates 5/11/26 - 5/15/26 on Linkedin Email Project Updates 5/11/26 - 5/15/26 linkHello Stakeholders,
Below are project updates from this week, as well as for the upcoming week (May11-15):- Tuesday’s storm brought some much-needed moisture but temporarily halted work for a few days. With the snow now melted, crews are focusing on cleaning up mud and excess water throughout the project area.
- On Monday, the concrete crew poured curb, gutter, and sidewalk along the east leg of West 10th Street on the south side adjacent to the apartment complex.
- Before the storm arrived, the pipe crew completed the tie-in and flow-filled the remaining section at 10th Street and Colorado Avenue. Crews are allowing the intersection time to dry before resuming work in that area.
- Connell Resources is also cleaning up the project staging area and removing excess materials in preparation for final site restoration once the project is completed, anticipated by mid-June 2026.
- The concrete crew will continue progressing west along the south side of 10th Street from Colorado Avenue to Douglas Avenue. Work will be completed one access point at a time to help residents maintain access to their properties. For the property with only a single access point, crews are coordinating closely with the resident and will use high-early-strength concrete so access is only impacted for one day.
- The base crew will return to continue reconstruction and cleanup work at the 10th Street and Colorado Avenue intersection. The concrete crew will also complete replacement sections of sidewalk, curb, gutter, and cross pans in the area.
- The base crew will also begin removing sections of the north half of 10th Street where additional drainage improvements are needed to carry water across the roadway from north to south.
Thank you for your patience as we enter the final weeks of this project - a major effort that began five years ago. More updates will be shared as we continue moving toward project completion.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.
Hello Stakeholders,
Below are project updates from this week, as well as for the upcoming week (May11-15):- Tuesday’s storm brought some much-needed moisture but temporarily halted work for a few days. With the snow now melted, crews are focusing on cleaning up mud and excess water throughout the project area.
- On Monday, the concrete crew poured curb, gutter, and sidewalk along the east leg of West 10th Street on the south side adjacent to the apartment complex.
- Before the storm arrived, the pipe crew completed the tie-in and flow-filled the remaining section at 10th Street and Colorado Avenue. Crews are allowing the intersection time to dry before resuming work in that area.
- Connell Resources is also cleaning up the project staging area and removing excess materials in preparation for final site restoration once the project is completed, anticipated by mid-June 2026.
- The concrete crew will continue progressing west along the south side of 10th Street from Colorado Avenue to Douglas Avenue. Work will be completed one access point at a time to help residents maintain access to their properties. For the property with only a single access point, crews are coordinating closely with the resident and will use high-early-strength concrete so access is only impacted for one day.
- The base crew will return to continue reconstruction and cleanup work at the 10th Street and Colorado Avenue intersection. The concrete crew will also complete replacement sections of sidewalk, curb, gutter, and cross pans in the area.
- The base crew will also begin removing sections of the north half of 10th Street where additional drainage improvements are needed to carry water across the roadway from north to south.
Thank you for your patience as we enter the final weeks of this project - a major effort that began five years ago. More updates will be shared as we continue moving toward project completion.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.
-
Weekly Update for 4/27/26 - 5/1/26
Share Weekly Update for 4/27/26 - 5/1/26 on Facebook Share Weekly Update for 4/27/26 - 5/1/26 on Twitter Share Weekly Update for 4/27/26 - 5/1/26 on Linkedin Email Weekly Update for 4/27/26 - 5/1/26 linkBelow are project updates from this week, as well as for the upcoming week (April 27th - May 1st):
- Installation of the inlets at Douglas Avenue and 10th Street has been completed.
- The concrete crew began curb, gutter, and sidewalk work at Douglas Avenue and 10th Street and will continue this week.
- Crews will continue working at Colorado Avenue and 10th Street under a full roadway closure. Due to numerous existing utilities in the area and the age of the infrastructure work is progressing slowly to install the large storm pipe and manholes.
- This week, crews will continue pouring curb, gutter, inlet tops, and sidewalks. They will also begin the new curb and gutter section along the south side of 10th Street ahead of milling and repaving that portion of roadway.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Below are project updates from this week, as well as for the upcoming week (April 27th - May 1st):
- Installation of the inlets at Douglas Avenue and 10th Street has been completed.
- The concrete crew began curb, gutter, and sidewalk work at Douglas Avenue and 10th Street and will continue this week.
- Crews will continue working at Colorado Avenue and 10th Street under a full roadway closure. Due to numerous existing utilities in the area and the age of the infrastructure work is progressing slowly to install the large storm pipe and manholes.
- This week, crews will continue pouring curb, gutter, inlet tops, and sidewalks. They will also begin the new curb and gutter section along the south side of 10th Street ahead of milling and repaving that portion of roadway.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

-
Project Updates for 4/20/26 - 4/24/26
Share Project Updates for 4/20/26 - 4/24/26 on Facebook Share Project Updates for 4/20/26 - 4/24/26 on Twitter Share Project Updates for 4/20/26 - 4/24/26 on Linkedin Email Project Updates for 4/20/26 - 4/24/26 linkBelow are project updates from this week, as well as for the upcoming week (April 20th-24th):
- Crews will continue installing inlets and storm pipe along West 10th Street (between Douglas Avenue and Colorado Avenue), as well as at the intersection of Colorado Avenue and 10th Street. This will complete a major tie-in to connect the west and east segments.
- Crews will also fill all abandoned Barnes Ditch bridge crossings at Colorado, Franklin, Roosevelt, Harrison, Grant, and Garfield Avenues. Once complete, the handrails will be removed and the crossings filled with concrete.
- Minor concrete repairs will be made before beginning extended curb and gutter work along the south side of 10th Street.
- The landscape contractor will be on site to restore disturbed areas, including the corners of intersections.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Below are project updates from this week, as well as for the upcoming week (April 20th-24th):
- Crews will continue installing inlets and storm pipe along West 10th Street (between Douglas Avenue and Colorado Avenue), as well as at the intersection of Colorado Avenue and 10th Street. This will complete a major tie-in to connect the west and east segments.
- Crews will also fill all abandoned Barnes Ditch bridge crossings at Colorado, Franklin, Roosevelt, Harrison, Grant, and Garfield Avenues. Once complete, the handrails will be removed and the crossings filled with concrete.
- Minor concrete repairs will be made before beginning extended curb and gutter work along the south side of 10th Street.
- The landscape contractor will be on site to restore disturbed areas, including the corners of intersections.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

-
Project Updates for 3/13/26 - 3/17/26
Share Project Updates for 3/13/26 - 3/17/26 on Facebook Share Project Updates for 3/13/26 - 3/17/26 on Twitter Share Project Updates for 3/13/26 - 3/17/26 on Linkedin Email Project Updates for 3/13/26 - 3/17/26 linkBelow are project updates from this week, as well as for the upcoming week (April 13th-17th):
- The pipe crew installed several inlets along West 10th Street between Colorado Avenue and Douglas Avenue on the south side of the roadway.
- The paving crew returned to the site and completed cleanup along Roosevelt Avenue, 10th Street (from Franklin to Harrison), the Roosevelt and 11th Street intersection, and 11th Street from Roosevelt to McKinley.
- After cleanup, the paving crew milled areas of the roadway in poor condition and improved edge transitions for smoother tie-ins.
- Crews then raised manholes and valve boxes and completed paving operations at the Roosevelt Avenue and 11th Street intersection, along 11th Street from Roosevelt to McKinley, on Roosevelt Avenue from 10th to 11th Street, and on 10th Street from Harrison to Roosevelt.
- Paving from 10th Street from Roosevelt to Franklin will occur next.
- The landscaping crew is expected to mobilize later the week of 4/13, to begin work at intersections, including landscape restoration, sprinkler repairs, and sod placement as needed.
- The concrete crew will replace two damaged curb sections at the radius of 11th Street and Roosevelt Avenue.
- The intersection of Colorado Avenue and 10th Street will be closed for approximately four weeks to allow for major utility work and pipe installation.
- Work will continue along 10th Street, including removal of old asphalt and concrete along the north side of the roadway, resident access to homes will be maintained.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Below are project updates from this week, as well as for the upcoming week (April 13th-17th):
- The pipe crew installed several inlets along West 10th Street between Colorado Avenue and Douglas Avenue on the south side of the roadway.
- The paving crew returned to the site and completed cleanup along Roosevelt Avenue, 10th Street (from Franklin to Harrison), the Roosevelt and 11th Street intersection, and 11th Street from Roosevelt to McKinley.
- After cleanup, the paving crew milled areas of the roadway in poor condition and improved edge transitions for smoother tie-ins.
- Crews then raised manholes and valve boxes and completed paving operations at the Roosevelt Avenue and 11th Street intersection, along 11th Street from Roosevelt to McKinley, on Roosevelt Avenue from 10th to 11th Street, and on 10th Street from Harrison to Roosevelt.
- Paving from 10th Street from Roosevelt to Franklin will occur next.
- The landscaping crew is expected to mobilize later the week of 4/13, to begin work at intersections, including landscape restoration, sprinkler repairs, and sod placement as needed.
- The concrete crew will replace two damaged curb sections at the radius of 11th Street and Roosevelt Avenue.
- The intersection of Colorado Avenue and 10th Street will be closed for approximately four weeks to allow for major utility work and pipe installation.
- Work will continue along 10th Street, including removal of old asphalt and concrete along the north side of the roadway, resident access to homes will be maintained.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

-
Project Updates for 4/6/26 - 4/10/26
Share Project Updates for 4/6/26 - 4/10/26 on Facebook Share Project Updates for 4/6/26 - 4/10/26 on Twitter Share Project Updates for 4/6/26 - 4/10/26 on Linkedin Email Project Updates for 4/6/26 - 4/10/26 linkBelow are project updates from this week, as well as for the upcoming week (April 6th-10th):
- Crews began work on West 10th Street, west of Colorado Avenue and installed the first inlet and connecting pipe to the existing main.
- A second crew is completing cleanup and backfilling along the new curb and gutter in the eastern portion of the project near Roosevelt Avenue and 11th Street.
- Beginning the week of 4/6, paving crews will return to mill and profile 10th Street, Roosevelt Avenue, and 11th Street, and begin reconstruction of larger sections at the 11th Street and Roosevelt Avenue intersection.
- The pipe crew will continue installing inlets and storm pipe along West 10th Street between Colorado Avenue and Douglas Avenue. Advance signage has been installed for the upcoming closure of the Colorado Avenue and 10th Street intersection. This closure is scheduled to begin April 13th and last approximately three weeks.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Below are project updates from this week, as well as for the upcoming week (April 6th-10th):
- Crews began work on West 10th Street, west of Colorado Avenue and installed the first inlet and connecting pipe to the existing main.
- A second crew is completing cleanup and backfilling along the new curb and gutter in the eastern portion of the project near Roosevelt Avenue and 11th Street.
- Beginning the week of 4/6, paving crews will return to mill and profile 10th Street, Roosevelt Avenue, and 11th Street, and begin reconstruction of larger sections at the 11th Street and Roosevelt Avenue intersection.
- The pipe crew will continue installing inlets and storm pipe along West 10th Street between Colorado Avenue and Douglas Avenue. Advance signage has been installed for the upcoming closure of the Colorado Avenue and 10th Street intersection. This closure is scheduled to begin April 13th and last approximately three weeks.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

-
Project Updates for 3/30/26 - 4/3/26
Share Project Updates for 3/30/26 - 4/3/26 on Facebook Share Project Updates for 3/30/26 - 4/3/26 on Twitter Share Project Updates for 3/30/26 - 4/3/26 on Linkedin Email Project Updates for 3/30/26 - 4/3/26 linkBelow are project updates from this week, as well as for the upcoming week (March 30th - April 3rd):
- The pipe crew completed the final tie-in from the inlet on 11th Street west of Roosevelt Avenue and will move to the West 10th Street segment, west of Colorado Avenue, the week of 3/30.
- The base and paving crews completed the remaining sections of 10th Street as well as areas on Roosevelt Avenue and a portion of 11th Street, east of Roosevelt Avenue.
- The concrete crew completed the remaining inlets, curb, gutter, and sidewalks on 10th Street, including installation of an ADA ramp at the northwest corner of 10th Street and Roosevelt Avenue.
- The pipe crew will begin operations along West 10th Street (west of Colorado Avenue), saw cutting and potholing to verify utility locations and potential underground conflicts. The section, between Colorado and Douglas Avenues will be closed to through traffic but remain open to local residents.
- The concrete crew will complete the final inlet on the east side of the project at 11th Street and Roosevelt Avenue.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Below are project updates from this week, as well as for the upcoming week (March 30th - April 3rd):
- The pipe crew completed the final tie-in from the inlet on 11th Street west of Roosevelt Avenue and will move to the West 10th Street segment, west of Colorado Avenue, the week of 3/30.
- The base and paving crews completed the remaining sections of 10th Street as well as areas on Roosevelt Avenue and a portion of 11th Street, east of Roosevelt Avenue.
- The concrete crew completed the remaining inlets, curb, gutter, and sidewalks on 10th Street, including installation of an ADA ramp at the northwest corner of 10th Street and Roosevelt Avenue.
- The pipe crew will begin operations along West 10th Street (west of Colorado Avenue), saw cutting and potholing to verify utility locations and potential underground conflicts. The section, between Colorado and Douglas Avenues will be closed to through traffic but remain open to local residents.
- The concrete crew will complete the final inlet on the east side of the project at 11th Street and Roosevelt Avenue.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

-
Project Updates for 3/23/26 - 3/27/26
Share Project Updates for 3/23/26 - 3/27/26 on Facebook Share Project Updates for 3/23/26 - 3/27/26 on Twitter Share Project Updates for 3/23/26 - 3/27/26 on Linkedin Email Project Updates for 3/23/26 - 3/27/26 linkBelow are project updates from this week, as well as for the upcoming week (March 23rd-27th):
- The pipe crew worked on two inlets at the intersection of Roosevelt Avenue and 10th Street last week. Progress was slow due to site conditions, but the installations have been completed.
- The concrete crew worked on inlets, curb, gutter, and sidewalks to catch up, with three remaining inlets to complete once the pipe crew finishes installation.
- Flyers have been distributed to all residents along West 10th Street, between Colorado Avenue and Douglas Avenue, with the anticipated closure of 10th Street to begin as early as Monday, March 23, 2026.
- The base crew is expected to return next week to begin work at the Roosevelt Avenue and 10th Street intersection and complete remaining sections from the previous round of base and paving.
- Following completion of base work, the paving crew will return to place remaining bottom layer of asphalt and begin mill and overlay operations on the remaining street sections, including 10th Street, Roosevelt Avenue, and 11th Street from Roosevelt Avenue to McKinley Avenue.
- Potholing and saw cutting may also occur next week along 10th Street west of Colorado Avenue to Douglas Avenue.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Below are project updates from this week, as well as for the upcoming week (March 23rd-27th):
- The pipe crew worked on two inlets at the intersection of Roosevelt Avenue and 10th Street last week. Progress was slow due to site conditions, but the installations have been completed.
- The concrete crew worked on inlets, curb, gutter, and sidewalks to catch up, with three remaining inlets to complete once the pipe crew finishes installation.
- Flyers have been distributed to all residents along West 10th Street, between Colorado Avenue and Douglas Avenue, with the anticipated closure of 10th Street to begin as early as Monday, March 23, 2026.
- The base crew is expected to return next week to begin work at the Roosevelt Avenue and 10th Street intersection and complete remaining sections from the previous round of base and paving.
- Following completion of base work, the paving crew will return to place remaining bottom layer of asphalt and begin mill and overlay operations on the remaining street sections, including 10th Street, Roosevelt Avenue, and 11th Street from Roosevelt Avenue to McKinley Avenue.
- Potholing and saw cutting may also occur next week along 10th Street west of Colorado Avenue to Douglas Avenue.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Follow Project
Project Timeline
-
Project Open House
Garfield-Harrison Project has finished this stageNov. 8, 2021
-
Phase 1
Garfield-Harrison Project has finished this stageJan. 17, 2022
-
Phase 2
Garfield-Harrison Project has finished this stageOct. 10, 2023
-
Phase 2C
Garfield-Harrison Project has finished this stagePhase 2c will begin April 1, 2024, weather permitting. Phase 2c will include:
- Street milling will begin March 25.
- A large diameter stormsewer pipe will be installed up to 5th Street and then east to Roosevelt. Excavation for the pipe will be extensive and require a full road closure.
- New waterline will be installed on 5th Street between California and Roosevelt Avenues.
-
Phase 3
Garfield-Harrison Project has finished this stageAugust 2024 - August 2025
-
Phase 4
Garfield-Harrison Project is currently at this stageAugust 2025 - end of 2026
Videos
-
Click here to play video
Find out more about the Garfield/Harrison project with this informative video.
-
Click here to play video
Drone footage of W. 1st Street taken November 2021 prior to Phase 1 construction. Ongoing videos will be created to show construction progress.
Drone footage of W. 1st Street taken November 2021 prior to Phase 1 construction. Ongoing videos will be created to show construction progress.
Photos
Documents
-
Notices
-
2025-04-25_NoticeofWork_Phase3_FINAL.pdf (334 KB) (pdf)
-
2024-11-26_Garfeild-Harrison-Project_Paving Notice.docx (201 KB) (docx)
-
Garfield-Harrison Phase 2c Flyer (8.5 x 11)_FINAL.pdf (2.84 MB) (pdf)
-
Garfield Harrison Postcard 4x6_Phase 2C_FINAL.pdf (1.54 MB) (pdf)
-
Post card mailing for Phase 2 (6.99 MB) (pdf)
-
Garfield Harrison Phase 1 Project FAQ (6.54 MB) (pdf)
-
2022_Residential_Letter_Safety-MH.pdf (94.1 KB) (pdf)
-
Detour map.pdf (247 KB) (pdf)
-
Who's Listening
-
Phone 970-962-2606 Email marc.lyons@cityofloveland.org -
Phone 970-962-2773 Email Eric.Lessard@cityofloveland.org -
Phone 970-962-2608 Email Illianna.Milldrum@cityofloveland.org







