Project weekly update 3/3/2025 - 3/7/2025

Hello Stakeholders!

Here are the project updates for this week (3/3-3/7).

  1. Potholing and survey are ongoing as we continue design on Phase 4.
  2. Stormsewer work will continue to the east of Roosevelt along 8th Street.
  3. Concrete work is also ongoing and street subgrade preparation will occur in areas to be paved in late March.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.