US 34 and Taft Avenue Intersection Improvement Project
The US 34 highway managed by the Colorado Department of Transportation (CDOT) is a regionally traveled road. In addition to serving as a main corridor for Lovelanders, it also heavily used by visitors and guests as the gateway to Rocky Mountain National Park.
According to the City’s traffic data, US 34/Eisenhower Boulevard has 28,000 daily commuters and 21,000 Taft Avenue commuters daily. With this information, as well as how many collisions occur through this heavily congested area, the City has worked to improve traffic flow and reduce congestion at one of Loveland’s busiest intersections.
Once complete, the US 34 and Taft Avenue Intersection Improvement Project will improve the intersection by providing:
- Two through lanes of traffic in each direction on North Taft Avenue (north and southbound).
- Double turn lanes
- Bike lanes, curb, gutter, and sidewalks to promote pedestrian and cyclist safety.
- An updated traffic signal at the US 34 and North Taft Avenue intersection, meeting current industry standards.
- Water and electric infrastructure enhancements to accommodate future utility demands.
This work will provide safer conditions on North Taft Avenue and the US 34/Eisenhower Boulevard intersection, as well as improve a multi-modal (walking, biking, driving and public transit) corridor along North Taft Avenue that’s part of the City’s larger Connect Loveland Master Plan.
Some history
The US 34 and Taft Avenue Intersection Improvement Project was introduced to the Loveland City Council in 1999. Throughout the years, the biggest hurdle for the project has been funding. The City found different funding sources to move the project forward over the years and is now able to move forward with allocated funding dedicated to the project. The City has acquired the homes along North Taft Avenue from 11th Street to Westshore Drive for the project, starting in 2021. In order to accomplish the improvements to widen Taft, additional rights-of-way and easements were required. The City acquired these properties to meet construction schedules and progress with an anticipated summer 2024 construction date—all of which is necessary to leverage federal grant funding opportunities.
Why now?
The project must start this summer 2024 to meet construction schedules and leverage federal grant funding opportunities.
What's next?
This project will entail four phasing stages. An overview of the phases is shown on the right sidebar under " Project Timeline" or "Documents."
Why are we doing this project?
After reviewing the crash data, including this area into Connect Loveland and reviewing the multi-modal accessibility of the intersection, the City looks forward to incorporating these much-needed improvements to one of Loveland’s busiest intersections.
How will this be funded?
The project will be supported by multiple funding streams collected over the past 10 years to move the project forward (2013-2023):
- Congestion Mitigation Air Quality Grant = $3,330,637
- TABOR Excess = $100,000
- General Fund = $2,220,829
- Allocated funds dedicated from 2021 - 2023.
- Capital Expansion Fees (CEF)= $2,935,828
- Developer fees dedicated to improving infrastructure for future expansion.
Stay Informed
To stay informed about this project, subscribe to our email list in the "Stay Informed" section. We understand construction can cause disruptions. Contact our project email at taftus34improvement@getinfonow.us or the hotline at 970-599-7788. Our team will respond to your concerns, comments, or questions within 24 hours. Thank you for your patience while this work is being completed.
The US 34 highway managed by the Colorado Department of Transportation (CDOT) is a regionally traveled road. In addition to serving as a main corridor for Lovelanders, it also heavily used by visitors and guests as the gateway to Rocky Mountain National Park.
According to the City’s traffic data, US 34/Eisenhower Boulevard has 28,000 daily commuters and 21,000 Taft Avenue commuters daily. With this information, as well as how many collisions occur through this heavily congested area, the City has worked to improve traffic flow and reduce congestion at one of Loveland’s busiest intersections.
Once complete, the US 34 and Taft Avenue Intersection Improvement Project will improve the intersection by providing:
- Two through lanes of traffic in each direction on North Taft Avenue (north and southbound).
- Double turn lanes
- Bike lanes, curb, gutter, and sidewalks to promote pedestrian and cyclist safety.
- An updated traffic signal at the US 34 and North Taft Avenue intersection, meeting current industry standards.
- Water and electric infrastructure enhancements to accommodate future utility demands.
This work will provide safer conditions on North Taft Avenue and the US 34/Eisenhower Boulevard intersection, as well as improve a multi-modal (walking, biking, driving and public transit) corridor along North Taft Avenue that’s part of the City’s larger Connect Loveland Master Plan.
Some history
The US 34 and Taft Avenue Intersection Improvement Project was introduced to the Loveland City Council in 1999. Throughout the years, the biggest hurdle for the project has been funding. The City found different funding sources to move the project forward over the years and is now able to move forward with allocated funding dedicated to the project. The City has acquired the homes along North Taft Avenue from 11th Street to Westshore Drive for the project, starting in 2021. In order to accomplish the improvements to widen Taft, additional rights-of-way and easements were required. The City acquired these properties to meet construction schedules and progress with an anticipated summer 2024 construction date—all of which is necessary to leverage federal grant funding opportunities.
Why now?
The project must start this summer 2024 to meet construction schedules and leverage federal grant funding opportunities.
What's next?
This project will entail four phasing stages. An overview of the phases is shown on the right sidebar under " Project Timeline" or "Documents."
Why are we doing this project?
After reviewing the crash data, including this area into Connect Loveland and reviewing the multi-modal accessibility of the intersection, the City looks forward to incorporating these much-needed improvements to one of Loveland’s busiest intersections.
How will this be funded?
The project will be supported by multiple funding streams collected over the past 10 years to move the project forward (2013-2023):
- Congestion Mitigation Air Quality Grant = $3,330,637
- TABOR Excess = $100,000
- General Fund = $2,220,829
- Allocated funds dedicated from 2021 - 2023.
- Capital Expansion Fees (CEF)= $2,935,828
- Developer fees dedicated to improving infrastructure for future expansion.
Stay Informed
To stay informed about this project, subscribe to our email list in the "Stay Informed" section. We understand construction can cause disruptions. Contact our project email at taftus34improvement@getinfonow.us or the hotline at 970-599-7788. Our team will respond to your concerns, comments, or questions within 24 hours. Thank you for your patience while this work is being completed.
-
FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project includes full closure for Phase 2 starting July 15
Share FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project includes full closure for Phase 2 starting July 15 on Facebook Share FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project includes full closure for Phase 2 starting July 15 on Twitter Share FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project includes full closure for Phase 2 starting July 15 on Linkedin Email FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project includes full closure for Phase 2 starting July 15 linkLOVELAND, Colo. – July 11, 2024 – The City of Loveland will begin Phase 2 construction for the US 34 and Taft Avenue Intersection Improvement project on Monday, July 15. Completion of this phase of the work is anticipated by early October, weather permitting. Phase 2 will include a full closure of S. Taft Avenue from US34/Eisenhower Boulevard to 8th Street, which includes daytime work from 7 a.m. to 7 p.m., Monday through Friday.
Construction will include adding an additional lefthand turn lanes on both northbound and southbound Taft Avenue heading onto US 34 to alleviate traffic congestion, as well as adding bike lanes, ADA sidewalks, curbs and gutters to prioritize pedestrian and cyclist safety. Additionally, Loveland Water and Power will replace the existing 12-inch cast iron pipes installed in the 1960s with new 12-inch PVC pipes. The new infrastructure will provide a pipe life expectancy of 100 years.
Detour Routes:
- Westbound traffic on US34/Eisenhower Boulevard will be diverted before the work area to Lincoln Avenue/US 287, with the option to use 29th Street or 1st Street.
- Eastbound traffic on US34/Eisenhower Boulevard will be diverted before the work area to Wilson Avenue, with the option to use 29th Street or 1st Street.
Phase 1 night work will overlap with Phase 2 daytime work and continue through late July to reduce two weeks off the project’s initial timeline. For both phases, daytime and nighttime construction will happen simultaneously. Nighttime work will be Sunday through Thursday from approximately 8 p.m. to 5 a.m., and daytime work will be Monday through Friday from 7 a.m. to 7 p.m.
“In order to maintain forward momentum on the project and avoid any unnecessary downtime for our contractors, there will be approximately a two-week period of overlap for Phases 1 and Phase 2. This operational adjustment will allow us to cut two weeks off of the overall timeline for the project,” said Construction Manager Bonar Crump.
Local access will be maintained for the surrounding neighborhood and businesses during the closure. Business access will remain open on US34/Eisenhower Boulevard and Taft Avenue. Throughout construction, commuters can expect delays and are encouraged to plan accordingly to allow enough time for their commute.
During nighttime work hours, construction noise from the equipment and temporary lights may be disruptive for residents in the area. Single lane closures are expected overnight. Traffic control signs and devices will be posted at all ends of the work areas along US 34/Eisenhower Boulevard and Taft Avenue. Personnel will be in the area to navigate traffic during working hours.
The remaining two phases of the project include the following:
- Phase 3 will include a full closure of Taft Avenue from US34/Eisenhower Boulevard to 22nd Street. The closure is currently planned from October through December. For this phase, there will be daytime construction from 7 a.m. – 7 p.m., Monday through Friday. Local access will be maintained for the surrounding neighborhood and businesses during the closure. Business access will remain open on US34/Eisenhower Boulevard and Taft Avenue. Construction will temporarily pause for the winter months.
- Phase 4 will include asphalt paving on US34/Eisenhower Boulevard from Prospect Avenue to Harlow Lane. Construction will resume in spring 2025. During construction, the public will be limited to single-lane closures. Nighttime work will be performed for this phase. Traffic should expect delays while navigating the area. Business access will remain open throughout Phase 4.
US 34 and Taft Avenue Intersection Improvement Detour Route
Additional project details including detour maps, images and other project updates, can be found at letstalkloveland.org/us34-and-taft-intersection-improvements. Residents who wish to sign up for weekly project updates, receive the latest information, or contact the project team can email taftus34improvement@getinfonow.us or 970-599-7788. If you see water line emergencies, please call 970-962-3456.
About
The US 34 and Taft Avenue Intersection Improvement Project was introduced to the Loveland City Council in 1999. Throughout the years, the biggest hurdle for the project has been funding. The City found different funding sources to move the project forward over the years and is now able to move forward with allocated funding dedicated to the project. The City has acquired and demolished the homes along the west side of Taft Avenue from 11th Street to US 34/Eisenhower Boulevard. In order to accomplish the improvements to widen Taft Avenue, additional rights-of-way and easements were required. The City acquired these properties to meet construction schedules and progress with an anticipated summer 2024 construction date—all of which is necessary to leverage federal grant funding opportunities.
Project Funding
The US 34 and Taft Avenue Intersection Improvement Project is funded by multiple funding streams collected over the past 10 years to move the project forward (2013-2023). Those funding streams include grants, TABOR, General Fund, Capital Expansion Fees and the Water Enterprise Fund. To learn more about the budget for this project, visit letstalkloveland.org/us34-and-taft-intersection-improvements.
-
FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project begins Phase 1 on July 8
Share FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project begins Phase 1 on July 8 on Facebook Share FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project begins Phase 1 on July 8 on Twitter Share FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project begins Phase 1 on July 8 on Linkedin Email FOR RELEASE: US 34 and Taft Avenue Intersection Improvement project begins Phase 1 on July 8 linkThe City of Loveland will begin Phase 1 construction for the US 34 and Taft Avenue Intersection Improvement project on Monday, July 8. This phase of the work will be completed by mid-July, weather permitting.
Phase 1 includes nighttime work along US 34/Eisenhower Boulevard between Westshore Drive and Prospect Avenue to remove light posts and medians to allow lane adjustments while providing safe working conditions for the crews. To maximize efficiencies and costs, the City’s Loveland Water and Power department will simultaneously replace the aging water line beneath the intersection of US 34/Eisenhower Boulevard and Taft Avenue.
“The enhancements at the intersection of Taft and US 34 are designed to boost safety and minimize delays for all modes of transportation, including drivers, cyclists, and pedestrians,” said assistant city engineer Keith Wakefield. “We’re excited to finally complete this 25-year-old project and construct these improvements for the Loveland community.”
The City has selected Coulson Excavating Company for the roadway improvements and Connell Resources for the waterline improvements as the contractors for construction. Typical working hours for Phase 1 work will be Sunday through Thursday from approximately 8 p.m. to 5 a.m. to limit traffic impacts for businesses, residents and commuters during the day.
During the working hours of this project, there will be construction noise from the equipment and temporary lights that may be disruptive for residents in the area. Single lane closures are expected overnight. Traffic control signs and devices will be posted at all ends of the work areas along US 34/Eisenhower Boulevard and Taft Avenue. Personnel will be in the area to navigate traffic during working hours.
The remaining three phases of the project include the following:
- Phase 2 will include a full closure of Taft Avenue from US34/Eisenhower Boulevard to 8th Street. The closure is currently planned from mid-July through October. For this phase, there will be daytime construction from 7 a.m. – 7 p.m., Monday through Friday. Local access will be maintained for the surrounding neighborhood and businesses during the closure. Business access will remain open on US34/Eisenhower Boulevard and Taft Avenue.
- Phase 3 will include a full closure of Taft Avenue from US34/Eisenhower Boulevard to 22nd Street. The closure is currently planned from October through December. For this phase, there will be daytime construction from 7 a.m. – 7 p.m., Monday through Friday. Local access will be maintained for the surrounding neighborhood and businesses during the closure. Business access will remain open on US34/Eisenhower Boulevard and Taft Avenue. Construction will temporarily pause for the winter months.
- Phase 4 will include asphalt paving on US34/Eisenhower Boulevard from Prospect Avenue to Harlow Lane. Construction will resume in spring 2025. During construction, the public will be limited to single-lane closures. Night work will be performed for this phase. Traffic should expect delays while navigating the area. Business access will remain open throughout Phase 4.
During Phases 2 and 3, detours for westbound traffic on US34/Eisenhower Boulevard will occur from Lincoln Avenue/US 287 to 29th Street or 1st Street, and eastbound traffic on US34/Eisenhower Boulevard from Wilson Avenue to 29th Street or 1st Street. Throughout construction, commuters should expect delays and are encouraged to plan accordingly to allow enough time for their commute.
US 34 and Taft Avenue Intersection Improvement Detour Route
Additional project details including detour maps, images and other project updates, can be found at letstalkloveland.org/us34-and-taft-intersection-improvements. Residents who wish to sign up for weekly project updates, receive the latest information, or contact the project team can email taftus34improvement@getinfonow.us or 970-599-7788. If you see water line emergencies, please call 970-962-3456.
About
The US 34 and Taft Avenue Intersection Improvement Project was introduced to the Loveland City Council in 1999. Throughout the years, the biggest hurdle for the project has been funding. The City found different funding sources to move the project forward over the years and is now able to move forward with allocated funding dedicated to the project. The City has acquired and demolished the homes along the west side of Taft Avenue from 11th Street to US 34/Eisenhower Boulevard. In order to accomplish the improvements to widen Taft Avenue, additional rights-of-way and easements were required. The City acquired these properties to meet construction schedules and progress with an anticipated summer 2024 construction date—all of which is necessary to leverage federal grant funding opportunities.
Project Funding
The US 34 and Taft Avenue Intersection Improvement Project is funded by multiple funding streams collected over the past 10 years to move the project forward (2013-2023). Those funding streams include grants, TABOR, General Fund, Capital Expansion Fees and the Water Enterprise Fund. To learn more about the budget for this project, visit letstalkloveland.org/us34-and-taft-intersection-improvements.
-
A second opportunity to learn about the US 34 and Taft Avenue Intersection Improvement project
Share A second opportunity to learn about the US 34 and Taft Avenue Intersection Improvement project on Facebook Share A second opportunity to learn about the US 34 and Taft Avenue Intersection Improvement project on Twitter Share A second opportunity to learn about the US 34 and Taft Avenue Intersection Improvement project on Linkedin Email A second opportunity to learn about the US 34 and Taft Avenue Intersection Improvement project linkApril 24 open house with residents and business owners surrounding a plot plan.
On Wednesday, April 24, 2024, the US 34 and Taft Avenue Intersection Improvement project successfully hosted 35 residents and business owners at the Public Works Administration Building. Thank you to all who attended and provided feedback, questions, comments, or concerns to our project team. The April 24 open house was dedicated to those within a 3,000-foot project radius who would be impacted by the work zones throughout construction. We appreciated the opportunity to connect with guests to address their concerns.
Another opportunity to learn about the project and connect with the team will be hosted at the Capital Improvement Projects (CIP) Fair from 4-6 p.m., Thursday, May 30, at the Beet Education Center, 201 E. 5th St.
The event will include the US 34 and Taft Avenue Intersection Improvement Project and other projects planned by the Public Works, Water and Power, and Parks and Recreation departments.
The CIP Fair will feature displays, construction timelines, phasing information, and opportunities for attendees to engage with City staff. Each project will include budget-related details to help the public understand how infrastructure projects are funded across the City.
Event Details:
- Date: Thursday, May 30
- Time: 4-6 p.m.
- Location: The Beet Education Center (201 E 5th St.)
- Department Participation: Public Works, Water and Power, Parks and Recreation, Cultural Services, Finance and North Front Range Metropolitan Planning Organization.
Don't miss out on this informative and engaging event! To learn more about the CIP Fair, visit go.lovgov.org/news-7580. The event is also listed on the City’s Facebook, Nextdoor, and X, formerly Twitter, channels. We look forward to seeing you there!
--
CONTACT:
- Illianna Milldrum, Communications & Engagement Specialist, 970-962-2608, illianna.milldrum@cityofloveland.org
-
Daytime sidewalk repairs planned for May 20
Share Daytime sidewalk repairs planned for May 20 on Facebook Share Daytime sidewalk repairs planned for May 20 on Twitter Share Daytime sidewalk repairs planned for May 20 on Linkedin Email Daytime sidewalk repairs planned for May 20 linkThe relocation of gas lines on Taft Avenue and US 34 is complete; however, two locations at the intersection will require sidewalk repairs. Construction will be located in front of the Village Inn and on the southwest corner of S. Taft Avenue and US 34.
This work will be performed from 10 a.m. to 3 p.m., Monday, May 20, weather permitting.
During the working hours of this project, there will be a single lane closure on US 34 heading westbound, starting before Westshore Drive to the Village Inn entrance. Another single lane closure will be on US 34 and Taft Avenue heading eastbound, impacting the right turn lane.
Traffic control signs will be posted at all ends of the work areas along US 34 and Taft Avenue.
To avoid the construction area, commuters can detour from US 287 to 29th Street or 1st Street heading westbound. For commuters heading east on US 34 and Taft Avenue, they can detour to Wilson Avenue and 29th Street or 1st Street.
We appreciate your patience and understanding while this temporary work is being performed and as we prepare for the intersection improvement project.
--CONTACT:
- Illianna Milldrum, Communications & Engagement Specialist, 970-962-2608, illianna.milldrum@cityofloveland.org
-
Night work for gas line relocations planned for April 1-25
Share Night work for gas line relocations planned for April 1-25 on Facebook Share Night work for gas line relocations planned for April 1-25 on Twitter Share Night work for gas line relocations planned for April 1-25 on Linkedin Email Night work for gas line relocations planned for April 1-25 linkThe Taft Avenue demolition work as part of the City’s North Taft Avenue Widening Project is now complete. Relocation of gas lines underground is the next phase of preliminary construction work. Xcel Energy and its contractor, Mears, will perform the work near US34 and Taft Avenue. The gas lines need to be lowered or relocated because they will conflict with the new infrastructure in the area.
To reduce traffic volume and limit impacts to businesses and the traveling public during the day, this work will be performed overnight from 9 p.m. to 5 a.m., Sunday through Thursday, from April 1 - 25, weather permitting. Alternating single-lane closures will be in place throughout construction in the following areas:
- Eisenhower/US34 from Loch Mount Drive to Harlow Lane heading westbound
- Taft Avenue from west 15th Street to First Bank
- Eisenhower/US34 from Prospect Avenue to Harlow Lane heading eastbound
Additionally, residents should expect delays while construction is being performed. Traffic control signs and personnel will be on site to navigate traffic during the working hours.
Throughout construction, there will be noise from the equipment while Mears relocates several gas lines. There will also be temporary lights in the area that may be disruptive.
We appreciate your patience and understanding while this work is being performed and as we prepare for the intersection improvement project.
Follow Project
Videos
-
Click here to play video US 34 and Taft Avenue Intersection Improvement Project - Phase 2 Overview Phase 2 of the US 34 and Taft Avenue Intersection Improvement Project has brought exciting updates, transforming one of Loveland’s busiest intersections. In collaboration with the City’s Public Works and Water and Power Departments, our team has accomplished the following: ✅ Replaced outdated 12-inch cast iron pipes with new, durable 12-inch PVC pipes and upgraded waterlines and valves. ✅ Installed brand-new traffic signal poles alongside electrical and communication utility upgrades. ✅ Reconstruction of southbound Taft Avenue, adding two new turning lanes, ADA-compliant sidewalks, curbs, and gutters. Want to learn more? Check out our project update video to hear from our team as they share the latest progress! Stay informed with project details, detour maps, and more, plus subscribe to the project newsletter at: go.lovgov.org/Taft-and-US34
-
Click here to play video US 34 and Taft Avenue Intersection Improvement Project Overview The US 34 and Taft Avenue Intersection Improvement Project is underway! This project addresses intersection improvements to the aging waterline and stormwater infrastructure, improving bike and pedestrian accesses, reducing congestion, and strengthening safety at one of Loveland’s busiest areas. US34/Eisenhower Boulevard is pivotal in Loveland's region transportation network. It serves not only as a main corridor for Lovelanders but as the gateway to Rocky Mountain National Park, attracting a significant number of visitors. Phase 1 of this project is anticipated to start on Monday, July 8.
Project Timeline
-
Demolition
US 34 and Taft Avenue Intersection Improvement Project has finished this stageOctober 2023
-
Phase 1, July 8 - Aug. 21, 2024
US 34 and Taft Avenue Intersection Improvement Project has finished this stagePhase 1 will include night work from 8 p.m. to 5 a.m. During this phase of construction, the intersection will be open to all directions of travel, with lane closures. Although night work will not affect peak traveling hours, commuters should expect delays in the area. Business access will remain open through Phase 1.
-
Phase 2, July 15 - October 2024
US 34 and Taft Avenue Intersection Improvement Project has finished this stagePhase 2 will include a full closure from US34/Eisenhower and south Taft Avenue to 8th Street. Local access will be maintained for the surrounding neighborhood and businesses during the closure. Business access will remain open on US34/Eisenhower.
Scheduled detours:
- Westbound - Detour from Lincoln Avenue/US 287 to 29th Street or 1st Street.
- Eastbound - Detour from Wilson Avenue to 29th Street or 1st Street.
-
Phase 3a, October - December 2024
US 34 and Taft Avenue Intersection Improvement Project has finished this stagePhase 3a will include a full closure from US34/Eisenhower and north Taft Avenue to 18th Street. Local access will be maintained for the surrounding neighborhood and businesses during the closure. Business access will remain open on US34/Eisenhower.
Scheduled detours:
- Westbound - Detour from Lincoln Avenue/US 287 to 29th Street or 1st Street.
- Eastbound - Detour from Wilson Avenue to 29th Street or 1st Street.
-
Winter Shutdown, December 2024 - March 2025
US 34 and Taft Avenue Intersection Improvement Project has finished this stageDue to unpredictable weather conditions in the winter months, the project will enter a temporary shutdown. At this time, operations on the project will halt, with a few small tasks completed along US 34 from Westshore Drive to Prospect Avenue.
-
Phase 3b and c, March - June 2025
US 34 and Taft Avenue Intersection Improvement Project is currently at this stagePhase 3b will involve replacing curbs, gutters, sidewalks, and improving roadway entry points on the north side of US 34/Eisenhower Boulevard, from Westshore Drive to east of Wendy’s. During non-peak travel hours, after the morning commute and before evening commute, the right westbound lane of US 34 will be closed, allowing one westbound lane of travel. During Phase 3b, business access will remain open. Once Phase 3b is completed in May, weather permitting, work will transition to N. Taft Avenue to complete the widening improvements, which will require full closure of N. Taft Avenue from US 34/Eisenhower Boulevard to 18th Street.
Scheduled detours:
- Westbound - Detour from Lincoln Avenue/US 287 to 29th Street or 1st Street.
- Eastbound - Detour from Wilson Avenue to 29th Street or 1st Street.
-
Phase 4, June - July 2025
this is an upcoming stage for US 34 and Taft Avenue Intersection Improvement ProjectPhase 4 will include asphalt paving on US34/Eisenhower from Prospect Avenue to Harlow Lane. During construction, the public will be limited to single-lane closures. Night work will be performed for this phase. Traffic should expect delays while navigating the area. Business access will remain open through Phase 4.
Photos
Documents
-
Notice of Work
-
2025-03-12_NoticeofWork_Phase3b-c_FINAL (949 KB) (pdf)
-
2024-12-10_NoticeofWork_WinterShutdown_FINAL.pdf (501 KB) (pdf)
-
2024-10-11_NoticeofWork_Phase3Closure_FINAL .pdf (524 KB) (pdf)
-
2024-08-21_Resident-Business_Notice of Work_Phase2NTaftAvenueConstruction_FINAL.pdf (272 KB) (pdf)
-
2024-07-31_Resident Notice of Work_FlaggerandDriverPassUpdate_FINAL.pdf (197 KB) (pdf)
-
2024-07-22_Business Notice of Work_PW-LWP-Phase1and2Updates_FINAL.pdf (200 KB) (pdf)
-
Resident-Business Notice of Work - Taft and US 34 - Phase2Closure_FINAL.docx (959 KB) (docx)
-
Resident Notice of Work - Taft and US 34 - Phase 1_FINAL .pdf (194 KB) (pdf)
-
Business Notice of Work - Taft and US 34 Xcel_FINAL.pdf (736 KB) (pdf)
-
Resident-Businesses Notice of Work - Taft and US 34 Xcel_FINAL.pdf (192 KB) (pdf)
-
DemoNoticeBusinesses_US34&TaftWidening_FINAL.pdf (197 KB) (pdf)
-
DemoNoticeResidents_US34&TaftWidening_FINAL.pdf (198 KB) (pdf)
-
-
Construction Phasing Flyers
-
Open House
-
July 2023 City Council Presentation
Previous Events and Meetings
-
October 2023
-
April 24 2024
-
May 30 2024
Who's Listening
-
Phone 970-962-2645 Email Bonar.Crump@cityofloveland.org -
Phone 970-962-2642 Email Mike.Jacobson@cityofloveland.org -
KW
Phone 970-962-3351 Email keith.wakefield@cityofloveland.org -
Phone 970-962-2608 Email Illianna.Milldrum@cityofloveland.org -
Phone 970-962-2604 Email Marcie.Willard@cityofloveland.org