Project weekly update 05/13/2024 - 05/17/2024

Hello Stakeholders!

Here are the project updates starting this week, 5/13

  1. Next week, work will begin installing the 18-inch lateral to the west on 5th Street. This process will be much faster compared to working with the 54-inch pipe.
  2. The waterline installation will follow the storm sewer installation.
  3. Concrete repairs and ADA ramp installations will work up Sheridan Avenue from 4th Street to 5th Street.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.