Project weekly update 05/27/2024 - 05/31/2024

Hello Stakeholders!

Here are the project updates starting this week, 5/27

  1. No work was performed on Monday, 5/27, due to the observance of Memorial Day.
  2. The stormsewer will continue to be installed between Franklin and Sheridan. Upon completion, the stormsewer will begin from Sheridan Avenue to Roosevelt Avenue
  3. Waterline installation will begin the first week of June following the stormsewer.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.