Hello Stakeholders!
Here are the project updates starting this week, 6/03:
- Storm sewer installation at Franklin Avenue & 5th Street will continue through the week.
- The waterline will begin following the storm sewer the following week.
- Concrete repairs and ADA-compliant handicap ramps will also be built concurrently on Sheridan Avenue in preparation for paving at the end of June.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.