Project weekly update 06/03/2024 - 06/07/2024

Hello Stakeholders!

Here are the project updates starting this week, 6/03:

  1. Storm sewer installation at Franklin Avenue & 5th Street will continue through the week.
  2. The waterline will begin following the storm sewer the following week.
  3. Concrete repairs and ADA-compliant handicap ramps will also be built concurrently on Sheridan Avenue in preparation for paving at the end of June.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.