Project weekly update 07/29/2024 - 08/02/2024
Hello Stakeholders!
Here are the project updates for this week (7/29 - 8/02)
- Waterlines will be getting tied in next week and excavations completed on 5th Street.
- Paving operations are upcoming.
- The next phase of construction will continue on Roosevelt Avenue.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.