  1. Waterline work for Phase 2c will be wrapping up and temporary water for Phase 3 will be installed next week.
  2. Concrete work on ADA ramps and curb & gutter will continue as we transition to work on Roosevelt Avenue.
  3. Paving operations will also continue as Phase 2c is completed.