Project weekly update 08/12/2024 - 08/16/2024
Hello Stakeholders!
Here are the project updates for this week (8/12 - 8/16)
- Temporary water will continue to be installed on Roosevelt up to 8th Street. Once water is shifted to the temporary system, residents will no longer be charged for water usage.
- A large 54” storm sewer will be installed going north of Roosevelt from 5th Street.
- Concrete work is ongoing, and paving operations will occur next Friday to lay down the bottom mat and bring it up to Roosevelt.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 08/12/2024 - 08/16/2024 on Facebook
Share Project weekly update 08/12/2024 - 08/16/2024 on Twitter
Share Project weekly update 08/12/2024 - 08/16/2024 on Linkedin
Email Project weekly update 08/12/2024 - 08/16/2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends