Project weekly update 08/19/2024 - 08/23/2024
Hello Stakeholders!
Here are the project updates for this week (8/19 - 8/23)
- Milling of asphalt between and 7th and 8th Street on Roosevelt Avenue will occur this week.
- Paving operations will continue as Phase 2 is completed.
- Installation of the 54” stormsewer pipe up Roosevelt Avenue from the 5th Street intersection will continue as Phase 3 is underway.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.