Project weekly update 08/26/2024 - 08/30/2024
Hello Stakeholders!
Here are the project updates for this week (8/26 - 8/30)
- Milling from 7th Street to 8th Street on Roosevelt Avenue has been done, and staging of the RCP pipe will continue.
- RCP Pipe installation from 5th Street to 7th Street continues.
- Landscape work on 5th Street will start Wednesday through Friday.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.