Project weekly update 08/26/2024 - 08/30/2024

Hello Stakeholders!

Here are the project updates for this week (8/26 - 8/30)

  1. Milling from 7th Street to 8th Street on Roosevelt Avenue has been done, and staging of the RCP pipe will continue.
  2. RCP Pipe installation from 5th Street to 7th Street continues.
  3. Landscape work on 5th Street will start Wednesday through Friday.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.