Project weekly update 09/16/2024 -09/20/2024

Hello Stakeholders!

Here are the project updates for this week (9/16-9/20).

  1. Paving complete on 5th Street from Franklin to Roosevelt. The street is open to traffic.
  2. Utility locates and potholing will continue ahead of the stormwater install.
  3. Install of the 54” stormwater pipe continues north of 5th Street to 7th Street on Roosevelt.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.