Project weekly update 09/16/2024 -09/20/2024
Hello Stakeholders!
Here are the project updates for this week (9/16-9/20).
- Paving complete on 5th Street from Franklin to Roosevelt. The street is open to traffic.
- Utility locates and potholing will continue ahead of the stormwater install.
- Install of the 54” stormwater pipe continues north of 5th Street to 7th Street on Roosevelt.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.