Project weekly update 1/13/2025 - 1/17/2025

Hello Stakeholders!

Here are the project updates for this week (1/13-1/17).

  1. There will be continued potholing and utility identification going on.
  2. Large diameter stormsewer pipe will continue to be installed on Roosevelt between 7th and 8th Street.
  3. A large underground water quality vault will be installed (via a crane) on Roosevelt south of 8th Street.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.comor 970-716-5155.

Thank you for your continued patience and support.