Project weekly update 1/20/2025 - 1/24/2025

Hello Stakeholders!

Here are the project updates for this week (1/20-1/24).

  1. Potholing and survey will be ongoing.
  2. Due to weather, there may not be construction work on Monday and possibly Tuesday.
  3. The water quality vault on Roosevelt will be installed the week after next.
  4. Inlet construction will continue on 7th Street and smaller diameter stormsewer will be installed on 8th Street.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.comor 970-716-5155.

Thank you for your continued patience and support.