Project weekly update 1/6/2025 - 1/10/2025

Hello Stakeholders!

Here are the project updates for this week (1/6-1/10).

  1. Crews will be installing large diameter 54” stormsewer pipe from the intersection of 8th and Roosevelt up to 9th Street.
  2. Inlet installations at 7th & Sheridan will be completed.
  3. The Carlsonator underground stormwater quality structure will be installed at 7th and Roosevelt.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.