Project weekly update 10/21/2024 - 10/25/2024
Hello Stakeholders!
Here are the project updates for this week (10/21-10/26).
- Continue installing storm pipe up Roosevelt Avenue to the Arkins Branch.
- Water line work will also start this week up Roosevelt Avenue from 5th to the Arkins Branch.
- No changes will occur to the traffic control until the project reaches 8th Street in a few weeks to a month.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.