Project weekly update 10/28/2024 -11/01/2024

Hello Stakeholders!

Here are the project updates for this week (10/28-11/01).

  1. Potholing and utility locates are ongoing
  2. Waterline installation work will continue on Roosevelt between 5th and 7th.
  3. Inlets and stormsewer will be installed at the intersection of 7th and Roosevelt.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.