Project weekly update 11/25/2024 - 11/29/2024
Hello Stakeholders!
Here are the project updates for this week (11/25-11/29).
- Potholing and survey are ongoing. Flyers for residents to be impacted by coming construction have been distributed.
- Work crews will be finishing work on 7th Street. Work will shift to Roosevelt Avenue and 8th Street.
- After Thanksgiving, 8th Street between Sheridan and Harrison, and also Roosevelt from 8th to 9th will have no parking signs posted and the streets will be milled.
- Paving on Roosevelt between 5th and 7th is planned for next week weather permitting.
- There will not be work on Thursday and Friday in observance of the holidays.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 11/25/2024 - 11/29/2024 on Facebook
Share Project weekly update 11/25/2024 - 11/29/2024 on Twitter
Share Project weekly update 11/25/2024 - 11/29/2024 on Linkedin
Email Project weekly update 11/25/2024 - 11/29/2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends