Project weekly update 11/25/2024 - 11/29/2024

Hello Stakeholders!

Here are the project updates for this week (11/25-11/29).

  1. Potholing and survey are ongoing. Flyers for residents to be impacted by coming construction have been distributed.
  2. Work crews will be finishing work on 7th Street. Work will shift to Roosevelt Avenue and 8th Street.
  3. After Thanksgiving, 8th Street between Sheridan and Harrison, and also Roosevelt from 8th to 9th will have no parking signs posted and the streets will be milled.
  4. Paving on Roosevelt between 5th and 7th is planned for next week weather permitting.
  5. There will not be work on Thursday and Friday in observance of the holidays.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.

Share Project weekly update 11/25/2024 - 11/29/2024 on Facebook Share Project weekly update 11/25/2024 - 11/29/2024 on Twitter Share Project weekly update 11/25/2024 - 11/29/2024 on Linkedin Email Project weekly update 11/25/2024 - 11/29/2024 link