Project weekly update 12/02/2024 - 12/06/2024
Hello Stakeholders!
Here are the project updates for this week (12/02-12/06):
The items that were completed last week and ready for this week:
- Potholes on Roosevelt and 9th will continue.
- Crews working on water line and storm at Sheridan and 7th.
- Roosevelt from 5th to the Church north of 7th has been paved.
Items for this week:
- Milling on Monday on 8th Street from Sheridan to Harrison and possible Roosevelt up to 9th Street.
- Continue installation of pipe on 7th Street at Sheridan to Franklin.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 12/02/2024 - 12/06/2024 on Facebook
Share Project weekly update 12/02/2024 - 12/06/2024 on Twitter
Share Project weekly update 12/02/2024 - 12/06/2024 on Linkedin
Email Project weekly update 12/02/2024 - 12/06/2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends