Project weekly update 12/02/2024 - 12/06/2024

Hello Stakeholders!

Here are the project updates for this week (12/02-12/06):

The items that were completed last week and ready for this week:

  1. Potholes on Roosevelt and 9th will continue.
  2. Crews working on water line and storm at Sheridan and 7th.
  3. Roosevelt from 5th to the Church north of 7th has been paved.

Items for this week:

  1. Milling on Monday on 8th Street from Sheridan to Harrison and possible Roosevelt up to 9th Street.
  2. Continue installation of pipe on 7th Street at Sheridan to Franklin.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.