- Waterline work will continue on 8th Street with a 12” valve to be installed at Roosevelt Avenue.
- Temporary water will be removed from the properties at 7th Street and Sheridan Avenue.
- Inlets and manholes will then be installed at this intersection following the waterline work.
- Street preparation and paving will be occurring on Roosevelt Avenue between 5th and 7th Streets.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 12/16/2024 - 12/20/2024 on Facebook
Share Project weekly update 12/16/2024 - 12/20/2024 on Twitter
Share Project weekly update 12/16/2024 - 12/20/2024 on Linkedin
Email Project weekly update 12/16/2024 - 12/20/2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends