Project weekly update 2/3/2025 - 2/7/2025

Hello Stakeholders!

Here are the project updates for this week (2/3-2/7).

  1. Utility locates and survey is ongoing.
  2. There will be continued stormsewer installation on 7th Street between Roosevelt Avenue and Franklin Avenue.
  3. Stormsewer installation on 8th Street east of Roosevelt Avenue will continue also.
  4. Concrete curb and ramps will begin installation at disturbed areas.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.

Thank you for your continued patience and support.