Project Weekly Update 4/14/25 - 4/18/25
Hello Stakeholders!
Here are the project updates for this week (4/14-4/18).
- Stormsewer installation will continue up to 9th Street on Roosevelt Avenue.
- Subgrade and street base preparation will be occurring in areas installations are complete.
- Potholing and utility investigations will be occurring early next week at the intersection of 8th and Colorado Ave.
Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.