Project Weekly Update 4/14/25 - 4/18/25

Hello Stakeholders!

Here are the project updates for this week (4/14-4/18).

  1. Stormsewer installation will continue up to 9th Street on Roosevelt Avenue.
  2. Subgrade and street base preparation will be occurring in areas installations are complete.
  3. Potholing and utility investigations will be occurring early next week at the intersection of 8th and Colorado Ave.

Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.