Project weekly update 4/15/2024-4/19/2024
Hello Stakeholders!
Here are the project updates starting next week, 4/15.
- Excavation work along N. Sheridan Avenue will pick up this coming week starting with installation of large storm sewer culverts. This will be followed by the waterline installation.
- Work will progress up 5th Street and then turn west, heading to N. Franklin Avenue.
Weather permitting, work activities are Monday-Friday, 7:00 am – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.