- Potholing activities and deliveries of concrete inlets and manholes will be ongoing next week.
- Curb & gutter and concrete repairs will also be ongoing on Roosevelt Avenue.
- Stormsewer installation will continue on Roosevelt.
- Roadway preparation and paving will also occur next week on 8th Street and Roosevelt Avenue dependent on weather.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com(External link)(External link) or 970-716-5155.
Thank you for your continued patience and support.
Share Project Weekly update 4/7/25 - 4/11/25 on Facebook
Share Project Weekly update 4/7/25 - 4/11/25 on Twitter
Share Project Weekly update 4/7/25 - 4/11/25 on Linkedin
Email Project Weekly update 4/7/25 - 4/11/25 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends