The Garfield Harrison Storm Drain Project work activities for this coming week (7/17-7/21) include:
- Crews are working on the waterline installation on W. 5th Street. Next week they will be working between Franklin Avenue and Colorado Avenue.
- Crews are also working on the storm sewer installation on Colorado Avenue. Work will continue between W. 4th Street and W. 5th Street.
- Bottom mat paving will be upcoming the week of July 24th, at W. 4th Street and Logan Avenue.
Weather permitting, work activities are Monday-Friday, 7am to 5pm.