Project weekly update for 6/5/23 - 6/9/23

CLOSED: This discussion has concluded.

The Garfield Harrison Storm Drain Project work activities for this coming week (6/5-6/9) include:

  1. Storm sewer and waterline crews are continuing to work on 4th Street and making good progress.
  2. Concrete curb, gutter, and sidewalk repairs are ongoing through next week.
  3. Bottom mat paving is to occur today or possibly Monday depending on weather at 4th Street & Sheridan Avenue.

Weather permitting, work activities are Monday-Friday, 7am to 5pm.