Weekly project updates: 04/07/2025 - 04/13/2025
Hello, Loveland!
Here are the project updates for the week (4/07/25-4/13/25):
- Fire line installations on Blocks 1 & 2 (Lincoln to Washington).
- Water meter tie-overs on Blocks 1 & 2 (Lincoln to Washington).
- Midblock pedestrian crossing on Block 1 (Jefferson to Washington) to minimize pedestrian access distances to businesses on the north side of Block 1.
- ADVANCE NOTICE: The E. 4th Street and Washington Avenue intersection will be closed for 2-3 weeks starting April 14, 2025. Detour and access information will be provided in a press release next week.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support as we revitalized 4th Street!
Share Weekly project updates: 04/07/2025 - 04/13/2025 on Facebook
Share Weekly project updates: 04/07/2025 - 04/13/2025 on Twitter
Share Weekly project updates: 04/07/2025 - 04/13/2025 on Linkedin
Email Weekly project updates: 04/07/2025 - 04/13/2025 link