Heart Improvement Plan (HIP Streets)
In 2009, the City of Loveland Public Works Department developed the conceptual plan for the Heart Improvement Plan (HIP Streets), which explored opportunities to enhance the streets within the historic core of Downtown Loveland. In 2017, after gathering public input, the plan was modernized to include a thoughtful and cost-effective approach to revitalizing 19 core blocks of Downtown Loveland.
The first phase of the Heart Improvement Plan – the 4th Street Revitalization – addresses the five blocks along 4th Street that extend from Garfield Avenue to Washington Avenue. The current effort is focused on improving 4th Street through streetscape enhancements, while the City of Loveland Water and Power Department works on upgrades to the utility infrastructure beneath the road. As this project is a significant effort, the City of Loveland and the Loveland Downtown Development Authority (DDA) have come together to finally bring this portion of the Heart Improvement Plan to fruition. We’re excited to reimagine our Downtown and it all starts with 4th Street.
Our project team is composed of local industry professionals who understand the importance of these improvements and are committed to making this a project our community can be proud of while embracing our historic core and creating a vibrant space that highlights our artistic community.
Project Vision
Create a functional, aesthetically pleasing, eclectic Downtown environment that facilitates business vitality, fosters a sense of community, and accentuates the identity of the Downtown commercial district.
Incorporate streetscaping as part of an existing major infrastructure project to minimize business impact and improve the built environment.
Project Impacts
By late February 2025, the City of Loveland aims to begin construction, starting with underground water and stormwater utility improvements. Once infrastructure improvements are complete, the City of Loveland will focus on surface improvements determined by the streetscape design. Between utility and streetscape improvements, each block is anticipated to take six to eight months to construct.
Pedestrian access to 4th Street businesses will remain open throughout the project, however, the road will be closed to vehicular traffic. Visitors can access the corridor by parking in lots along 5th Street and by using other nearby designated on-street parking. Visit the downtown parking webpage for a map of available parking options.
Updates
- Adopted Concept Plans (2009)
- Parking Studies (2018/2019)
- Revised Modernization Plan (2017)
- Infrastructure Assessment (2019)
- 4th Street Construction Design and Drawings (2023)
- Parking study updated
- Present updated plans to LRFA, City Planning Commission, Loveland Parks and Recreation, APP, City Management and DDA Board (07/2023-08/2023)
- First Open House at The Foundry to review public input (08/23/2023)
- Second Open House at the Desk Chair Workspace to gather additional input (12/12/2023)
- City Council Update (01/23/2024)
Project Goals
- Focus on Economic Vitality
- Attract new downtown visitors and patrons to encourage tourism
- Minimize construction disruption
- Finish the project with no business loss or claims
- Allow for efficient access, parking and circulation
- Catalyze business potential in under-utilized areas
- Create a Comfortable and Inviting Downtown Experience Unique to Loveland
- Create a safe environment that is activated at night and day
- Develop a vibrant, engaging and unique streetscape as a regional destination
- Capitalize on artistic spirit and attitude towards placemaking
- Build upon the unique Downtown Loveland identity
- Incorporate art and culture in design and user experience
- Identity and History, unique to Loveland
- Create a Flexible and Adaptable Streetscape
- Flexible and functional space for a variety of uses
- Allow for ease of seasonal programming needs
- Inviting and appealing place for a broad demographic to stimulate diverse businesses
- Design and build an easily maintained space
- Create more safe and comfortable walking/pedestrian zones
- Foster Partnerships for Long Term Success
- Provide for sustained stakeholder engagement
- Ensure Downtown Business support throughout project
Project Funding
On Tuesday, Nov. 19, 2024, Loveland’s City Council unanimously approved using Certificates of Participation (COPs) to help fund the Heart Improvement Plan’s 4th Street Revitalization project. The $24.5 million project will be paid for through a mix of Utility Enterprise Funds and COPs. Utility Enterprise Funds (Stormwater, Water and Power) will contribute $12 million, while the remaining $12.5 million will come from COPs paid by the Downtown Development Authority (DDA). No General Funds will be used for this project.
Stay Informed During Construction
Whether you live outside downtown or are directly affected by the construction, we have project updates tailored to your needs.
- General Public Updates: Receive updates on essential project news, major milestones, city-wide impacts, and opportunities to get involved in marketing and community events.
- Downtown Business/Resident Updates: Receive detailed information about construction impacts, traffic changes, neighborhood-specific updates, and how your business can participate in marketing campaigns and support programs.
To sign up for the project newsletter, join the Heart Improvement Plan Email List. To contact the project team, call the Public Works Department at 970-962-2524 or email HIPStreets@cityofloveland.org. Please allow at least 24-48 hours for a response. Thank you!
In 2009, the City of Loveland Public Works Department developed the conceptual plan for the Heart Improvement Plan (HIP Streets), which explored opportunities to enhance the streets within the historic core of Downtown Loveland. In 2017, after gathering public input, the plan was modernized to include a thoughtful and cost-effective approach to revitalizing 19 core blocks of Downtown Loveland.
The first phase of the Heart Improvement Plan – the 4th Street Revitalization – addresses the five blocks along 4th Street that extend from Garfield Avenue to Washington Avenue. The current effort is focused on improving 4th Street through streetscape enhancements, while the City of Loveland Water and Power Department works on upgrades to the utility infrastructure beneath the road. As this project is a significant effort, the City of Loveland and the Loveland Downtown Development Authority (DDA) have come together to finally bring this portion of the Heart Improvement Plan to fruition. We’re excited to reimagine our Downtown and it all starts with 4th Street.
Our project team is composed of local industry professionals who understand the importance of these improvements and are committed to making this a project our community can be proud of while embracing our historic core and creating a vibrant space that highlights our artistic community.
Project Vision
Create a functional, aesthetically pleasing, eclectic Downtown environment that facilitates business vitality, fosters a sense of community, and accentuates the identity of the Downtown commercial district.
Incorporate streetscaping as part of an existing major infrastructure project to minimize business impact and improve the built environment.
Project Impacts
By late February 2025, the City of Loveland aims to begin construction, starting with underground water and stormwater utility improvements. Once infrastructure improvements are complete, the City of Loveland will focus on surface improvements determined by the streetscape design. Between utility and streetscape improvements, each block is anticipated to take six to eight months to construct.
Pedestrian access to 4th Street businesses will remain open throughout the project, however, the road will be closed to vehicular traffic. Visitors can access the corridor by parking in lots along 5th Street and by using other nearby designated on-street parking. Visit the downtown parking webpage for a map of available parking options.
Updates
- Adopted Concept Plans (2009)
- Parking Studies (2018/2019)
- Revised Modernization Plan (2017)
- Infrastructure Assessment (2019)
- 4th Street Construction Design and Drawings (2023)
- Parking study updated
- Present updated plans to LRFA, City Planning Commission, Loveland Parks and Recreation, APP, City Management and DDA Board (07/2023-08/2023)
- First Open House at The Foundry to review public input (08/23/2023)
- Second Open House at the Desk Chair Workspace to gather additional input (12/12/2023)
- City Council Update (01/23/2024)
Project Goals
- Focus on Economic Vitality
- Attract new downtown visitors and patrons to encourage tourism
- Minimize construction disruption
- Finish the project with no business loss or claims
- Allow for efficient access, parking and circulation
- Catalyze business potential in under-utilized areas
- Create a Comfortable and Inviting Downtown Experience Unique to Loveland
- Create a safe environment that is activated at night and day
- Develop a vibrant, engaging and unique streetscape as a regional destination
- Capitalize on artistic spirit and attitude towards placemaking
- Build upon the unique Downtown Loveland identity
- Incorporate art and culture in design and user experience
- Identity and History, unique to Loveland
- Create a Flexible and Adaptable Streetscape
- Flexible and functional space for a variety of uses
- Allow for ease of seasonal programming needs
- Inviting and appealing place for a broad demographic to stimulate diverse businesses
- Design and build an easily maintained space
- Create more safe and comfortable walking/pedestrian zones
- Foster Partnerships for Long Term Success
- Provide for sustained stakeholder engagement
- Ensure Downtown Business support throughout project
Project Funding
On Tuesday, Nov. 19, 2024, Loveland’s City Council unanimously approved using Certificates of Participation (COPs) to help fund the Heart Improvement Plan’s 4th Street Revitalization project. The $24.5 million project will be paid for through a mix of Utility Enterprise Funds and COPs. Utility Enterprise Funds (Stormwater, Water and Power) will contribute $12 million, while the remaining $12.5 million will come from COPs paid by the Downtown Development Authority (DDA). No General Funds will be used for this project.
Stay Informed During Construction
Whether you live outside downtown or are directly affected by the construction, we have project updates tailored to your needs.
- General Public Updates: Receive updates on essential project news, major milestones, city-wide impacts, and opportunities to get involved in marketing and community events.
- Downtown Business/Resident Updates: Receive detailed information about construction impacts, traffic changes, neighborhood-specific updates, and how your business can participate in marketing campaigns and support programs.
To sign up for the project newsletter, join the Heart Improvement Plan Email List. To contact the project team, call the Public Works Department at 970-962-2524 or email HIPStreets@cityofloveland.org. Please allow at least 24-48 hours for a response. Thank you!
-
Weekly project update 6/1/26 - 6/7/26
Share Weekly project update 6/1/26 - 6/7/26 on Facebook Share Weekly project update 6/1/26 - 6/7/26 on Twitter Share Weekly project update 6/1/26 - 6/7/26 on Linkedin Email Weekly project update 6/1/26 - 6/7/26 linkHello Stakeholders!
Here are the project updates for the week of 6/1/26 – 06/7/26:
-
Cleveland Avenue
- Concrete work has been completed on the south side of Cleveland at the 4th Street intersection, and traffic lanes and on-street parking are now open.
- Concrete work has been completed on the south side of Cleveland at the 4th Street intersection, and traffic lanes and on-street parking are now open.
-
Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Sidewalk and boulder seatwall work continues. Concrete paving is nearing completion.
-
Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Electrical conduit and light pole foundations are nearing completion.
- Grading begins in preparation for concrete bollard bands and paving.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Hello Stakeholders!
Here are the project updates for the week of 6/1/26 – 06/7/26:
-
Cleveland Avenue
- Concrete work has been completed on the south side of Cleveland at the 4th Street intersection, and traffic lanes and on-street parking are now open.
- Concrete work has been completed on the south side of Cleveland at the 4th Street intersection, and traffic lanes and on-street parking are now open.
-
Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Sidewalk and boulder seatwall work continues. Concrete paving is nearing completion.
-
Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Electrical conduit and light pole foundations are nearing completion.
- Grading begins in preparation for concrete bollard bands and paving.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
-
Cleveland Avenue
-
Weekly project update 5/25/26 - 5/31/26
Share Weekly project update 5/25/26 - 5/31/26 on Facebook Share Weekly project update 5/25/26 - 5/31/26 on Twitter Share Weekly project update 5/25/26 - 5/31/26 on Linkedin Email Weekly project update 5/25/26 - 5/31/26 linkHello Stakeholders!
Here are the project updates for the week of 5/25/26-5/31/26:
- No work Monday, May 25th in observance of Memorial Day
- Cleveland Avenue
- West on-street parking closures between E. 4th and E. 5th Streets.
- East on-street parking closures between Backstage Alley and E. 6th Street.
- East/southbound lane closure at E. 4th Street daily from 8:30 AM – 3:30 PM; open at night/early mornings.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, electric conduit and concrete work, including panel replacements in the roadway.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls and streetlight bases.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Power work is complete and the alley is reopened.
- A dumpster will still be present behind 209 E. 4th St.
- Backstage Alley (west of Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- CenturyLink conduit installations.
- Cleveland Ave. and E 6thSt. (non-project related work)
- Utility investigations and potholing work is complete.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Hello Stakeholders!
Here are the project updates for the week of 5/25/26-5/31/26:
- No work Monday, May 25th in observance of Memorial Day
- Cleveland Avenue
- West on-street parking closures between E. 4th and E. 5th Streets.
- East on-street parking closures between Backstage Alley and E. 6th Street.
- East/southbound lane closure at E. 4th Street daily from 8:30 AM – 3:30 PM; open at night/early mornings.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, electric conduit and concrete work, including panel replacements in the roadway.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls and streetlight bases.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Power work is complete and the alley is reopened.
- A dumpster will still be present behind 209 E. 4th St.
- Backstage Alley (west of Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- CenturyLink conduit installations.
- Cleveland Ave. and E 6thSt. (non-project related work)
- Utility investigations and potholing work is complete.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
-
Weekly project update 5/18/26 - 5/24/26
Share Weekly project update 5/18/26 - 5/24/26 on Facebook Share Weekly project update 5/18/26 - 5/24/26 on Twitter Share Weekly project update 5/18/26 - 5/24/26 on Linkedin Email Weekly project update 5/18/26 - 5/24/26 linkHello Loveland!
Here are the project updates for the week of 5/18/26-5/24/26:
• Block 1 (Washington to Jefferson)
o Flagging operations at 4th & Washington Ave. for storm system jetting.
• Block 3 (Lincoln to Cleveland Ave.)
o Block remains closed to vehicle traffic; businesses are open to pedestrian access.
o Boulder seatwalls, electric conduit and concrete work, including panel replacements in the roadway.
• Block 4 (Cleveland to N. Railroad Ave.)
o Block remains closed to vehicle traffic; businesses are open to pedestrian access.
o Power conduit and light pole base installations.
• Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
o Daily/workday closures and limited access.
o Electric meter replacements and transformer upgrades.
• Backstage Alley (west of Cleveland Ave.) (non-project related work)
o Daily/workday closures and limited access.
o CenturyLink conduit installations.
• Cleveland Ave. and E 6th St. (non-project related work)
o On-street parking closures and lane shifts.
o Utility investigations and potholing.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Hello Loveland!
Here are the project updates for the week of 5/18/26-5/24/26:
• Block 1 (Washington to Jefferson)
o Flagging operations at 4th & Washington Ave. for storm system jetting.
• Block 3 (Lincoln to Cleveland Ave.)
o Block remains closed to vehicle traffic; businesses are open to pedestrian access.
o Boulder seatwalls, electric conduit and concrete work, including panel replacements in the roadway.
• Block 4 (Cleveland to N. Railroad Ave.)
o Block remains closed to vehicle traffic; businesses are open to pedestrian access.
o Power conduit and light pole base installations.
• Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
o Daily/workday closures and limited access.
o Electric meter replacements and transformer upgrades.
• Backstage Alley (west of Cleveland Ave.) (non-project related work)
o Daily/workday closures and limited access.
o CenturyLink conduit installations.
• Cleveland Ave. and E 6th St. (non-project related work)
o On-street parking closures and lane shifts.
o Utility investigations and potholing.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
-
Weekly project update 5/11/26 - 5/17/26
Share Weekly project update 5/11/26 - 5/17/26 on Facebook Share Weekly project update 5/11/26 - 5/17/26 on Twitter Share Weekly project update 5/11/26 - 5/17/26 on Linkedin Email Weekly project update 5/11/26 - 5/17/26 linkHello Loveland —
Here are the project updates for the week of 5/11/26 - 5/17/26:
- Lincoln Avenue
- West on-street parking closures between E. 3rd Street and Sweetheart Alley.
- West lane closure at E. 4th Street: Daily (Monday through Friday) from 8:30 AM – 3:30 PM.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, irrigation installations and concrete work.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Storm sewer, power conduit and light pole base installations.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- Electric meter replacements and transformer upgrades.
- Backstage Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- CenturyLink conduit installations.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Hello Loveland —
Here are the project updates for the week of 5/11/26 - 5/17/26:
- Lincoln Avenue
- West on-street parking closures between E. 3rd Street and Sweetheart Alley.
- West lane closure at E. 4th Street: Daily (Monday through Friday) from 8:30 AM – 3:30 PM.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, irrigation installations and concrete work.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Storm sewer, power conduit and light pole base installations.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- Electric meter replacements and transformer upgrades.
- Backstage Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- CenturyLink conduit installations.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
- Lincoln Avenue
-
Update as of 5/4/26: Lincoln Avenue
Share Update as of 5/4/26: Lincoln Avenue on Facebook Share Update as of 5/4/26: Lincoln Avenue on Twitter Share Update as of 5/4/26: Lincoln Avenue on Linkedin Email Update as of 5/4/26: Lincoln Avenue linkSidewalk replacement work on Lincoln Avenue has been rescheduled due to expected inclement weather this week.
To maintain the overall project schedule, the following traffic and parking impacts are planned for May 11–15:
- West on‑street parking closures between E. 3rd Street and Sweetheart Alley
-
West lane closure at E. 4th Street, 8:30 AM–3:30 PM daily
- Flaggers will assist pedestrians crossing Lincoln Avenue
- Standard signal phasing will be in place during evenings
- Please follow pedestrian fencing and signage directing people walking through the area
Sidewalk replacement work on Lincoln Avenue has been rescheduled due to expected inclement weather this week.
To maintain the overall project schedule, the following traffic and parking impacts are planned for May 11–15:
- West on‑street parking closures between E. 3rd Street and Sweetheart Alley
-
West lane closure at E. 4th Street, 8:30 AM–3:30 PM daily
- Flaggers will assist pedestrians crossing Lincoln Avenue
- Standard signal phasing will be in place during evenings
- Please follow pedestrian fencing and signage directing people walking through the area
-
Weekly project update 5/4/26 - 5/10/26
Share Weekly project update 5/4/26 - 5/10/26 on Facebook Share Weekly project update 5/4/26 - 5/10/26 on Twitter Share Weekly project update 5/4/26 - 5/10/26 on Linkedin Email Weekly project update 5/4/26 - 5/10/26 linkHello Loveland,
Here are the project updates for next week (5/4/26-5/10/26):
- Lincoln Avenue
- West on-street parking closures between E. 3rd Street and Sweetheart Alley
- West lane closure at E. 4th Street: 8:30 AM – 3:30 PM on Monday, May 5 and Wednesday, May 7.
- Block 2 (Jefferson to Lincoln Ave.)
- On-street parking closed.
- Block will be closed to vehicles for approximately one day for landscaping installations. Sidewalks will remain open.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls and concrete.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Storm sewer, power conduit and light pole base installations.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- Electric meter replacements and transformer upgrades.
- Backstage Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- CenturyLink conduit installations.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Hello Loveland,
Here are the project updates for next week (5/4/26-5/10/26):
- Lincoln Avenue
- West on-street parking closures between E. 3rd Street and Sweetheart Alley
- West lane closure at E. 4th Street: 8:30 AM – 3:30 PM on Monday, May 5 and Wednesday, May 7.
- Block 2 (Jefferson to Lincoln Ave.)
- On-street parking closed.
- Block will be closed to vehicles for approximately one day for landscaping installations. Sidewalks will remain open.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls and concrete.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Storm sewer, power conduit and light pole base installations.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- Electric meter replacements and transformer upgrades.
- Backstage Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- CenturyLink conduit installations.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
- Lincoln Avenue
-
Weekly project update 4/27/26 - 5/3/26
Share Weekly project update 4/27/26 - 5/3/26 on Facebook Share Weekly project update 4/27/26 - 5/3/26 on Twitter Share Weekly project update 4/27/26 - 5/3/26 on Linkedin Email Weekly project update 4/27/26 - 5/3/26 linkHello Stakeholders!
Here are the project updates for this week (4/27/26-5/3/26).
- Crews will occasionally begin work as early as 5-6 AM to install building thresholds before businesses open.
- Block 1 (Washington to Jefferson Ave.)
- On-street parking closed.
- Block will be closed to vehicles for approximately one day for landscaping installations. Sidewalks will remain open.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, concrete and electric work.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Storm sewer and power conduit installations.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- Electric meter replacements and transformer upgrades.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Hello Stakeholders!
Here are the project updates for this week (4/27/26-5/3/26).
- Crews will occasionally begin work as early as 5-6 AM to install building thresholds before businesses open.
- Block 1 (Washington to Jefferson Ave.)
- On-street parking closed.
- Block will be closed to vehicles for approximately one day for landscaping installations. Sidewalks will remain open.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, concrete and electric work.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Storm sewer and power conduit installations.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- Electric meter replacements and transformer upgrades.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
-
Weekly project update 4/20/26 - 4/26/26
Share Weekly project update 4/20/26 - 4/26/26 on Facebook Share Weekly project update 4/20/26 - 4/26/26 on Twitter Share Weekly project update 4/20/26 - 4/26/26 on Linkedin Email Weekly project update 4/20/26 - 4/26/26 linkHello Stakeholders!
Here are the project updates for this week (4/20/26-4/26/26).
- Cleveland Avenue
- Parking closures and alternating lane sifts for striping activities.
- Major work on Cleveland will be completed this week!
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Boulder seatwalls, concrete and electric work.
- Block 4 (Cleveland to north Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Storm sewer and power conduit installations.
- North Railroad Avenue (east)
- Intersection is closed
- Utility installation
- Block 5 (Railroad Avenue (west) to Garfield Avenue.)
- Block will be closed to vehicles for approximately four days for landscaping installations. Sidewalks will remain open.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HIPStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Hello Stakeholders!
Here are the project updates for this week (4/20/26-4/26/26).
- Cleveland Avenue
- Parking closures and alternating lane sifts for striping activities.
- Major work on Cleveland will be completed this week!
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Boulder seatwalls, concrete and electric work.
- Block 4 (Cleveland to north Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Storm sewer and power conduit installations.
- North Railroad Avenue (east)
- Intersection is closed
- Utility installation
- Block 5 (Railroad Avenue (west) to Garfield Avenue.)
- Block will be closed to vehicles for approximately four days for landscaping installations. Sidewalks will remain open.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HIPStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
- Cleveland Avenue
-
Weekly project update 4/13/26 - 4/19/26
Share Weekly project update 4/13/26 - 4/19/26 on Facebook Share Weekly project update 4/13/26 - 4/19/26 on Twitter Share Weekly project update 4/13/26 - 4/19/26 on Linkedin Email Weekly project update 4/13/26 - 4/19/26 linkHello, Loveland!
Here are the project updates for this week (4/13/26-4/19/26).
- Cleveland Avenue
- Southbound Cleveland Avenue will remain in a single-lane configuration.
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Boulder seatwall, concrete and electric work.
- Non-project related façade work (209 E. 4th Street). Sidewalk impacts.
- Block 4 (Cleveland to N. Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Fireline installations.
- Storm sewer installations.
- Block 5 (Railroad Avenue west to Garfield Avenue)
- Landscaping installations.
- N. Railroad Avenue (east)
- Intersection closure (Area 1 below).
- Utility installations.
- Painters Alley (non-project related)
- Vault installation, Loveland Utilities.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HIPStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Hello, Loveland!
Here are the project updates for this week (4/13/26-4/19/26).
- Cleveland Avenue
- Southbound Cleveland Avenue will remain in a single-lane configuration.
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Boulder seatwall, concrete and electric work.
- Non-project related façade work (209 E. 4th Street). Sidewalk impacts.
- Block 4 (Cleveland to N. Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Fireline installations.
- Storm sewer installations.
- Block 5 (Railroad Avenue west to Garfield Avenue)
- Landscaping installations.
- N. Railroad Avenue (east)
- Intersection closure (Area 1 below).
- Utility installations.
- Painters Alley (non-project related)
- Vault installation, Loveland Utilities.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HIPStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
- Cleveland Avenue
-
Weekly project update 4/6/26 - 4/12/26
Share Weekly project update 4/6/26 - 4/12/26 on Facebook Share Weekly project update 4/6/26 - 4/12/26 on Twitter Share Weekly project update 4/6/26 - 4/12/26 on Linkedin Email Weekly project update 4/6/26 - 4/12/26 link
Stay Informed (Custom)
Project Timeline
-
Design
Heart Improvement Plan (HIP Streets) has finished this stageSummer 2023 – Fall 2024
-
Construction Start
Heart Improvement Plan (HIP Streets) is currently at this stageFebruary 24, 2025 - February 2026
-
Finish
this is an upcoming stage for Heart Improvement Plan (HIP Streets)November 2026
FAQs
-
Trees
- What are the main reasons the project chose to remove the existing trees instead of incorporating them into the new design?
- What are the varieties of the new trees and why were they chosen for this project?
- What are the variety of plants/bushes/grasses and why were they chosen?
- Are any of the varieties of trees / plants native to Colorado?
- What's the tree growth rate and what's the approximate size of trees that will be planted?
- How will the new irrigation system be installed and what will the water requirements to keep the new garden beds alive?
-
General
- HIP Streets is a project that has been discussed for many years. What triggered the launch of the 4th Street portion of the project?
- What is happening to the plaza at the former Mr. Neats?
- How is the project being funded?
- What are some of the major street and sidewalk changes that have been considered for the corridor?
- What is the plan for the pocket park at 4th and Lincoln?
- How will artwork, both existing and new, be incorporated into the final project?
-
Parking
-
Bike Access
Videos
-
Click here to play video
Heart Improvement Plan: Century-old waterline pipe gets upgrade at Railroad Avenue and 4th Street
In February 2026, City of Loveland Utilities replaced a century-old, 10-inch, cast-iron water pipe beneath the tracks at Railroad and 4th with a new 12-inch PVC pipe, set within a larger steel casing for protection. The older pipe, buried a mere four feet below and across the railway tracks, has supplied water to the residents and businesses of Fourth Street since 1924—from serving a population of around 5,600 to 85,000 people today. The construction is part of an ambitious downtown renovation project called the 4th Street Revitalization Project, the first phase of the comprehensive Heart Improvement Plan (HIP Streets) that centers on upgrading and improving deteriorating infrastructure such as utilities, roads and sidewalks in the “heart” of downtown Loveland.
-
Click here to play video
Heart Improvement Plan - Downtown Parking
Navigating downtown Loveland during construction? We’ve got you covered.
If you’re looking to access 4th Street in between Lincoln and Cleveland, the Foundry Parking Garage is a great parking option, offering quick and convenient access with a pass-through via the Rialto Bridge Project, available Monday–Friday from 6 a.m. to 9 p.m.
Downtown businesses remain open and ready to welcome you. Come support your favorite downtown Loveland establishments and check out the improvements!
For additional parking options and easy-to-follow parking maps, visit our website, lovgov.org/HIPStreets.
-
Click here to play video
Heart Improvement Plan | 4th Street Revitalization: Construction Update - September 2025
The Heart Improvement Plan began its first phase in February 2025, replacing aging utility infrastructure and launching 4th Street’s revitalization. The project started on the east end of 4th Street with Block 1 (Washington to Jefferson Avenues) and Block 2 (Jefferson to Lincoln Avenues). Groundbreaking of Block 5 (Railroad to Garfield Avenues) followed in mid-May.
✅ The underground utilities that have been replaced in the first two blocks are the existing 100+ year old water line, all of the storm sewer infrastructure, new electrical conduits for street lights, event power, communications and traffic.
✅ New concrete curbs and planters have been poured in Blocks 1 and 2. Sandstone seat-walls and art plinths have been placed along the street for sculptures provided by Art in Public Places (four per block).
✅ All utilities including water, storm sewer, electric and communications have been run across the 4th Street and Lincoln Avenue intersection, and a new transformer is being placed at the northeast corner to supply the new lighting and power along 4th Street.
✅ Concrete paving of the road in the first two blocks has started. Crews have shifted to Phase 1B on Block 1, which focuses on the sidewalk and street-scaping portion of the project.
✅ Water and stormwater work have been completed in Block 5. Electrical lines and conduit are currently being installed for streetlights, event power, communications and traffic.
✅ In Block 5, stone seat walls and art plinths will soon be placed. Crews will then move to curbs, planters, and concrete paving.
Stay informed with project details, maps, and subscribe to the project newsletter at: lovgov.org/HIPStreets.
-
Click here to play video
Heart Improvement Plan | 4th Street Revitalization's Groundbreaking
On Wednesday, February 26, the City of Loveland and the Loveland Downtown Development Authority took a step toward investing in downtown Loveland with a groundbreaking of the 4th Street Revitalization Project— the first piece of part of the Heart Improvement Plan (HIP Streets). As a whole, HIP Streets has been discussed for decades, where the project's focus is updating critical underground infrastructure for reliability and safety, addressing ADA accommodations, and cultivating a more pedestrian-friendly atmosphere to bring more visitors and businesses downtown.
Speakers included the City of Loveland's Mayor Jacki Marsh, Mayor Pro Tem Jon Mallo, City Engineer Nicole Hahn, City Water Engineer Donald Cecil and DDA Executive Director Sean Hawkins. The event welcomed partners, downtown businesses, current and previous City staff, and others who helped bring this vision to life.
As construction progresses, stay in the loop by visiting lovgov.org/HIPStreets.
-
Click here to play video
Heart Improvement Plan | 4th Street Revitalization Project: Project Overview
The Heart Improvement Plan | 4th Street Revitalization project welcomes the community in on a more in-depth view of the improvements coming to downtown Loveland. The project aims to bring new utility infrastructure and streetscape enhancements to transform downtown Loveland into a vibrant gathering space that fosters business vitality. ✨
Before construction begins, the project team sat down with the Loveland Downtown Development Authority, local business owners along 4th Street and City staff to share about the upcoming improvements and what the project will bring to our beloved downtown. The project will begin construction on Monday, Feb. 24. Although Lincoln to Garfield Avenue will be under construction, pedestrian accesses and business entrances will always be maintained. We welcome the community to come downtown and check out the progress!
Documents
-
Notices
-
2025-10-10_Washington Avenue and 4th Street Southbound Closure (2.81 MB) (pdf)
-
2025-04-21_DirectMailer_RESIDENT_FINAL.pdf (574 KB) (pdf)
-
2025-01-06_Door to Door Letter_HipStreets_TO MAIL (427 KB) (pdf)
-
2025-01-02_Notice of Work_XcelEnergy_4th_Lincoln to Jefferson (880 KB) (pdf)
-
Notice of Work - November 2024 Striping_FINAL (321 KB) (pdf)
-
-
Project Newsletters
-
Funding
-
Letters of Support
-
Letter of Support Chamber of Commerce HIP (51.7 KB) (pdf)
-
Historic Preservation Commission Letter of Support (666 KB) (pdf)
-
Transportation Advisory Board Letter of Support (663 KB) (pdf)
-
Citizens_ Finance Advisory Commission Resolution of Support (638 KB) (pdf)
-
VAC letter of support_DDA 10162024 (2.27 MB) (docx)
-
-
City Council Meetings
-
AIR-102611 - Feb. 4, 2025 (178 KB) (pdf)
-
Ordinance - Feb. 4, 2025 (128 KB) (pdf)
-
AIR-102564 - Nov. 14, 2024 (180 KB) (pdf)
-
Ordinance - Nov. 14, 2024 (227 KB) (pdf)
-
Att 2 Preliminary Offering Statement-compressed (943 KB) (pdf)
-
Att 3 Certificate Purchase Agreement (1.04 MB) (pdf)
-
Att 4 Trust Indenture (1.25 MB) (pdf)
-
Att 5 Site and Improvement Lease Agreement (832 KB) (pdf)
-
Att 6 Lease Purchase Agreement (1.12 MB) (pdf)
-
Att 7 Cooperation Agreement between the City _ the DDA (731 KB) (pdf)
-
Att 8 Continuing Disclosure Certificate (756 KB) (pdf)
-
-
Presentations
-
Parking
Who's Listening
-
Phone 970-962-2558 Email michelle.aschenbrenner@cityofloveland.org -
Phone 970-962-3702 Email donald.cecil@cityofloveland.org -
Phone 970-699-2856 Email SHawkins@lovelandpartnership.org -
Phone 970-541-0605 Email apowell@lovelandpartnership.org -
Phone 970-962-2608 Email illianna.milldrum@cityofloveland.org
Events and Meetings on This Topic
-
March 09 2026
-
February 26 2025
-
February 18 2025
-
February 04 2025
-
December 03 2024
-
November 19 2024
-
November 13 2024
-
September 24 2024
-
September 17 2024
-
January 23 2024
-
December 12 2023
-
September 21 2023
-
September 12 2023
-
August 23 2023
















