Weekly project updates: 4/21/2025 - 4/25/2025
Hello, Loveland!
Here are the project updates for next week (4/21/25-4/25/25):
- Block 1 waterline construction is complete! (Washington to Jefferson Avenue). Crews are now focused on waterline construction in Block 2 (Jefferson to Lincoln Avenues).
- The E. 4th Street & Washington Avenue intersection is fully closed and will remain closed for an additional two weeks. Waterline tie-ins at the intersection are complete and crews are working on storm drain connections. Completion of the storm manholes will allow storm water in 4th Street to continue west.
- ADVANCE NOTICE: Block 5 (Garfield to Railroad Avenue) construction will start early May.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support as we revitalized 4th Street!
Share Weekly project updates: 4/21/2025 - 4/25/2025 on Facebook
Share Weekly project updates: 4/21/2025 - 4/25/2025 on Twitter
Share Weekly project updates: 4/21/2025 - 4/25/2025 on Linkedin
Email Weekly project updates: 4/21/2025 - 4/25/2025 link